Cylinder Mold Filling and Rodding Dispute

ACI Strength Testing · Put your knowledge to work in context.

All case studies

Cylinder Mold Filling and Rodding Dispute

A technician is casting 6x12 in. cylinders from a slump of 1.5 in. concrete. The technician fills the mold in two layers and rods each layer 25 times with a 5/8 in. rod, then taps the mold with a mallet. A second technician argues that three layers and 25 strokes per layer are required, and that the rod should be 3/4 in. The first technician also leaves the cylinders outdoors at 45°F overnight without a cover. The next morning, the cylinders show a 0.5 in. settlement at the top and some surface drying. The lab supervisor must decide whether the cylinders are acceptable for 28-day testing.

1. Identify the procedural errors in casting and initial curing.

Read the worked answer

For a 6x12 in. cylinder, ASTM C31 requires filling in three layers of approximately equal volume, each rodded 25 times with a 5/8 in. diameter rod (for 6-in. cylinders). The first technician used two layers, which is non-compliant, and the second technician's claim of a 3/4 in. rod is incorrect for 6-in. molds (3/4 in. is for larger molds). Tapping the mold with a mallet is allowed to close voids but should not substitute for rodding. Initial curing must be at 60-80°F and protected from moisture loss; leaving cylinders uncovered at 45°F overnight violates both temperature and moisture requirements, causing the 0.5 in. settlement and surface drying. These errors compromise the 28-day strength and make the cylinders unsuitable for acceptance testing.

2. What should the supervisor do with these cylinders, and what is the correct procedure going forward?

Read the worked answer

The supervisor should reject the cylinders for acceptance testing because curing temperature was below 60°F and moisture was not maintained, both of which can reduce strength. The cylinders may be kept for informational purposes only, clearly labeled. Going forward: fill 6x12 in. molds in three equal layers, rod each layer 25 times with a 5/8 in. rod, tap the sides to release air, strike off the top, and cover immediately. Initial curing must be 60-80°F with moisture retention (plastic cover or wet burlap) for 24-48 hours, then transport to the lab. Record curing temperatures. If the concrete is still being placed, cast a new set of cylinders per ASTM C31 and ensure the field curing box maintains temperature.