Regulatory Notification and Waste Disposal
You are managing an asbestos abatement project in a state that has its own OSHA-approved State Plan and also administers an NESHAP program. The project involves removing 200 linear feet of 6-inch diameter asbestos-containing pipe insulation (friable) from a school building. The building will be demolished after abatement. The project is scheduled to start in 10 working days. You have submitted the required notification to the state agency. However, the client informs you that the building is actually going to be renovated, not demolished, and the abatement is now scheduled to begin in 5 working days. The client also wants to dispose of the waste in a local landfill that accepts construction debris.
1. What regulatory notifications and revisions are required, and what are the deadlines?
Read the worked answer
Under NESHAP, a renovation notification must be submitted at least 10 working days before the start of work. Since the start date has changed and the project is now a renovation, you must submit a revised notification as soon as possible, but no later than 10 working days before the new start date. However, if the new start date is only 5 working days away, you cannot meet the 10-working-day requirement; you must contact the regulatory agency to explain the emergency and get approval. Under the State Plan, there may be additional notification requirements. You must also update the notification to reflect the change from demolition to renovation. The waste disposal must be at a landfill permitted to accept asbestos-containing waste; a local construction debris landfill is likely not permitted, so you must arrange for proper disposal at a Subtitle D landfill that accepts asbestos waste, following NESHAP waste shipment requirements.
2. What are the waste handling and disposal requirements for the asbestos pipe insulation?
Read the worked answer
The waste must be wetted and sealed in leak-proof containers (e.g., 6-mil polyethylene bags or drums) labeled with the required warning. The containers must be transported by a licensed waste hauler to a permitted landfill. You must complete a waste shipment record (WSR) and ensure the landfill signs and returns it. The waste must be covered or kept wet during loading and unloading. The landfill must be authorized to accept asbestos waste. Since the insulation is friable, it must be handled carefully to prevent fiber release.