Scope of inspection and QA

Welding inspection verifies that fabrication follows the approved design, code, and contract. Quality assurance (QA) is the planned system that prevents nonconformance; quality control (QC) is the inspection and testing that detects it. Candidates must know the inspection and test plan (ITP), hold points, witness points, surveillance, and document review. A hold point stops work until the authorized inspector signs release. A witness point requires notification but normally does not stop work if the inspector is absent, unless the contract says otherwise.

Inspection begins before welding: verify WPS availability, welder qualification, consumable storage and baking, joint preparation, fit-up, preheat, and calibration of measuring and NDE equipment. During welding, monitor process variables, interpass temperature, cleaning, and root condition. After welding, verify dimensions, profile, NDE completion, PWHT records, and traceability.

Traps

  • Confusing QA with QC, or treating a witness point as a hold point.
  • Assuming inspection transfers quality responsibility away from the fabricator.
  • Accepting a procedure or welder without checking qualification scope.
  • Missing calibration status or consumable control records.
  • Applying project acceptance criteria when the code or contract specifies a different criterion.

Worked rule

If an ITP lists 'hold' at fit-up, the inspector must document acceptance before welding. If the item is 'witness,' notify the inspector; absent a contractual stop, work may proceed. Always read the contract definition, because some owners upgrade witness points to hold points.