A coastal mandal in Krishna district draws drinking water from a 12-km pipeline fed by a infiltration gallery on the riverbank. For three years the gallery's chloride reading in May has risen: 340 mg/L, then 410, then 520 mg/L, against the 250 mg/L permissible limit. The executive engineer has three options costed: (a) shift the gallery 4 km upstream and lay new pipeline at Rs 9.2 crore, protecting supply for 15 years; (b) install a 2 MLD desalination plant at Rs 4.1 crore plus Rs 60 lakh annual running cost and 1.4 MW of power; (c) do nothing this year and issue tanker supply in May–June at Rs 35 lakh per season. The mandal has 28,000 residents, 60% dependent on this scheme; groundwater in the habitation is already at 1,800 mg/L chloride. The state's coastal salinity ingression is projected to advance 2 km inland per decade under current extraction.

1. Which option should the engineer recommend, and on what decision criteria?

Read the worked answer

The recommendation must be built on life-cycle cost per protected person-year, not on lowest first cost.

  • (a) Upstream shift: Rs 9.2 crore / (28,000 × 15) ≈ Rs 219 per person-year, and it addresses the cause (moving ahead of the salinity front) rather than the symptom.
  • (b) Desalination: Rs 4.1 crore + 15 × Rs 0.6 crore = Rs 13.1 crore / (28,000 × 15) ≈ Rs 312 per person-year, plus 1.4 MW of continuous load and brine disposal on an already saline coast.
  • (c) Tankers: Rs 35 lakh × 15 = Rs 5.25 crore, but delivers no reliable year-round supply and leaves 40% of residents on 1,800 mg/L groundwater - this is the highest health cost, lowest capital cost trap.

Criteria to state explicitly: (i) does the option buy time ahead of a front moving 2 km/decade - only (a) does; (ii) recurring fiscal exposure - (b) locks the state into power and O&M forever; (iii) equity - the 40% not on the scheme remain exposed under all options unless the grid is extended.

So recommend (a) plus extension of the grid to the remaining 40%, financed partly by avoiding the desalination O&M. The judgement being tested is refusing the politically attractive 'plant' and the cheap 'tankers' in favour of the option that is cheapest per person-year and attacks the cause.

2. The MLA pressures for the desalination plant because it is visible and can be inaugurated. How should the engineer respond without being insubordinate?

Read the worked answer

The engineer should not frame this as a confrontation of 'technical truth vs politics'. The professional move is to convert the dispute into a shared decision with written trade-offs:

  1. Put the three options on one page with life-cycle cost, per-person-year cost, time to commissioning, power requirement, and risk of failure. Numbers, not adjectives.
  2. Offer the MLA a visible win inside the technically sound option - e.g., the upstream gallery, new pipeline and the 40% grid extension can be inaugurated too, and the MLA can claim the larger coverage.
  3. State the risk of (b) plainly: recurring O&M of Rs 60 lakh/year is the first line cut in a budget squeeze, and a plant that stops is worse than no plant.
  4. Escalate only if overruled in writing - record the advice in the file so accountability is not silently transferred.

The ethics being tested is integrity plus prudence: the officer owes the political executive honest advice, owes the public the cheapest safe water, and owes the institution a documented record. Refusing to speak is a dereliction; leaking to the press is disloyalty; silently complying is corruption of the technical function.