Configuring Make-to-Order vs. Make-to-Stock for a Custom Product Line

SCOR-P · Put your knowledge to work in context.

All case studies

Configuring Make-to-Order vs. Make-to-Stock for a Custom Product Line

A furniture manufacturer sells two lines through the same channel. Standard line: 40 SKUs, stable demand, 5-day customer promise, currently made to stock. Custom line: effectively infinite configurations (fabric, finish, dimensions), 6-week customer promise, currently made to order with a 3-week quoted lead time that is missed 35% of the time. Both lines share one plant, one finishing line, and a constrained upholstery cell. The custom line's order-entry errors (wrong fabric/finish codes) cause 12% of rework. Sales wants to promise 3 weeks on custom to win deals; the plant says the shared bottleneck cannot absorb it. Inventory of standard line is 45 days; custom line carries almost none.

1. Recommend the appropriate decoupling point for each line and how to protect the shared bottleneck.

Read the worked answer

Treat the two lines differently because their order penetration points and variability profiles differ.

  • Standard line: keep make-to-stock with the decoupling point at finished goods. Stable demand and a 5-day promise justify finished-goods buffer; 45 days is likely excessive and should be reset against service targets rather than left as-is.
  • Custom line: the decoupling point should sit at a configurable sub-assembly / pre-finish stage (postponement) rather than raw material or finished goods. Pre-build common frames and neutral bases, then apply fabric/finish/dimension late. This shortens the customer-facing lead time without stocking infinite variants.

Bottleneck protection: the upholstery cell is the constraint, so schedule it with explicit capacity reservation split between lines, and do not let custom promise dates consume capacity implicitly. Improve the order-entry/configurator accuracy to remove the 12% rework, which is pure capacity recovered at the constraint. Only after rework is cut and postponement is in place should sales quote 3 weeks - and the quote should be driven by available capacity at the constraint, not by sales ambition.

2. Sales argues that promising 3 weeks is a competitive necessity. How do you respond with a supply chain configuration logic?

Read the worked answer

Reframe: the promise is a configuration and capacity decision, not a marketing one. A 3-week promise with 35% misses is already damaging credibility; shortening the quote without changing the configuration will raise miss rates, not win sustainable deals.

Path to a credible shorter promise:

  1. Reduce the customer-facing lead time via postponement - pre-position neutral sub-assemblies so the post-order work is finish/assembly only.
  2. Recover constraint capacity - eliminate the 12% rework through configurator validation; that is capacity at the bottleneck without new capital.
  3. Quote from capacity - publish lead time by capacity bucket at the upholstery cell, with a premium/expedite tier if sales needs faster.

Then the promise can move toward 3 weeks as a consequence of the configuration change. Committing to the number first inverts the logic and pushes the plant to violate the constraint, which degrades both lines.