Advising a Client Who Wants to Skip the Permit
A plumber is asked to install a new 2000-litre rainwater tank connected to toilet flushing and a new below-ground stormwater line on a sloping block. The homeowner says a neighbour did the same 'without any paperwork' and asks the plumber to 'just do it' and backdate the compliance certificate to before the slab pour so the builder's inspection passes. The plumber knows the stormwater discharge point is unclear and the site may need a legal point of discharge confirmed by the water authority. The homeowner is impatient: the builder's inspection is in three days. The plumber has not yet lodged any paperwork and has no written contract.
1. How should the plumber respond to the backdating request, and what advice should be given about the approval process?
Read the worked answer
The plumber must refuse to backdate. A compliance certificate must reflect the date the work was actually completed and the state it was in. Backdating to satisfy a builder's inspection is falsification of a prescribed document - a serious offence that can cost the licence, regardless of who asked.
The correct advice: lodge the certificate for the work actually done, and if the inspection is imminent, tell the builder and homeowner the true status. For the stormwater, the legal point of discharge must be confirmed with the relevant water authority before connecting; guessing creates a drainage problem and possible liability. The tank-to-toilet connection also needs the appropriate approval and backflow protection.
The plumber should put this advice in writing, note that the homeowner instructed the shortcut, and proceed only with compliant work. Declining the backdating is not losing the job - it is protecting both parties.
2. The homeowner insists there is no time for approvals. What practical options can the plumber offer that keep the job moving without breaching obligations?
Read the worked answer
Offer sequencing rather than shortcuts. The plumber can complete the internal work that does not depend on the discharge point (tank set-down, internal pipework to the toilet, backflow device) and lodge the certificate for that portion, while the stormwater connection waits for the authority's confirmation. The builder's inspection can proceed on the completed scope with an honest written status note.
Alternatively, the plumber can seek an urgent response from the water authority, document the request, and give the homeowner a realistic timeline in writing. If the homeowner still refuses, the plumber should decline the non-compliant portion and record why.
The key advice point: 'no time' is not a defence to unapproved work, and a plumber who certifies work not done or not approved carries the risk, not the homeowner who pressured them.