The Shell Company, the Land Lease, and the Missing Permit

Azerbaijan Bar Advocate Qualification · Put your knowledge to work in context.

All case studies

The Shell Company, the Land Lease, and the Missing Permit

Company A, registered in a low-tax jurisdiction, holds a 49-year lease over 12 hectares of agricultural land in Azerbaijan through a local subsidiary, Company B. Company B wants to build a processing plant on 3 of the hectares. The land is classified as agricultural. A neighboring village council objects, saying the land was privatized irregularly in 2015 and that a protected water source lies beneath part of the plot. Company B has an environmental impact assessment but no separate water-use permit. Construction has not begun. The investor wants to start in 60 days.

1. What land-use and permitting issues must be resolved before construction?

Read the worked answer

The advocate must first verify the lawful basis of the lease and the 2015 privatization, because a defective title undermines everything downstream. Changing the use of agricultural land for a plant generally requires a formal change of designation or a specific permit; building on agricultural land without it is unlawful. The environmental impact assessment is necessary but not sufficient: if the plot overlaps a protected water source or a sanitary protection zone, a separate water-use or water-protection approval and possibly a positive conclusion from the competent authority are required. The advocate should obtain the cadastral extract, the lease, the privatization documents, and the zoning classification, and confirm whether any protected-area restrictions apply.

2. How should the advocate address the village council's objection?

Read the worked answer

The advocate should not treat the objection as merely political. She should verify the factual claims: the privatization record, any court challenges, and the status of the water source. If the privatization is valid, the advocate should document that and respond to the council in writing with the legal basis. If there is a genuine defect or a protected zone, the advocate must advise the client of the risk and explore alternatives such as relocating the plant footprint or seeking the required approvals. Concealing the issue would expose the client to later invalidation and the advocate to liability.

3. What should the advocate advise about the 60-day timeline?

Read the worked answer

The advocate should advise that the timeline is unrealistic unless the change-of-use and water approvals are already in process, and should set out a realistic sequence: title verification, change of designation, water-protection approval, and building permit. She should warn that starting construction without approvals risks stop-work orders, fines, and demolition. The advocate should give the client a written risk assessment and let the client decide, while refusing to assist in circumventing the permit requirements.