BGCSE Geography (Botswana Senior Secondary Education BSSE): Housing on the Flood Plain

BGCSE Geography · Put your knowledge to work in context.

All case studies

Housing on the Flood Plain

A coastal town of 45,000 people needs 2,000 new homes in 10 years. Flat land is scarce: the only large site is 60 hectares of low-lying former marsh beside a river and 1.5 m above sea level. The site floods in about one year in five. A ridge site 4 km inland is steeper, has shallow soils and is 90 m higher, but has no road and is 3 km from the nearest school. The council has a fixed budget and a 10-year deadline. Residents already living near the marsh say drainage is poor and roads flood. Sea level is rising slowly, and storms are becoming more intense.

1. Compare the marsh site and the ridge site for housing.

Read the worked answer

Marsh site

  • Advantages: flat, large (60 ha), close to existing services, cheaper to build on, road access likely.
  • Disadvantages: floods one year in five, only 1.5 m above sea level, rising sea level and stronger storms increase risk, poor drainage already affects nearby homes. Building 2,000 homes would put people and property in a hazard zone and could worsen flooding by paving over storage.

Ridge site

  • Advantages: 90 m higher, far less flood risk, better long-term safety as sea level rises.
  • Disadvantages: steeper slopes raise construction cost, shallow soils limit foundations and septic systems, no road, 3 km from school, so car dependence and travel cost rise.

Judgement: the ridge is safer but slower and costlier; the marsh is cheaper but risky. A mixed approach is most realistic.

2. Recommend a strategy and justify it against the budget and deadline.

Read the worked answer

A workable strategy is most homes on the ridge, with limited, flood-proofed development on the marsh.

  1. Ridge: build the majority of homes, but phase road access first. Use foundations suited to shallow soil, and cluster housing to reduce road length. Provide a school bus or small primary school to cut the 3 km gap.
  2. Marsh: allow a smaller number of homes only if raised on fill or stilts above flood level, with retention ponds and no building in the lowest parts. Keep open space for flood storage.
  3. Sequencing: start ridge access and drainage now, because the 10-year deadline is tight.

Justification: the ridge avoids placing 2,000 homes in a one-in-five-year flood zone, which would be hard to defend as sea level rises. The marsh can absorb some demand but should not carry the main load. If the ridge road cannot be funded, the council should reduce the housing target rather than crowd the flood plain.

3. What further information would most change your recommendation?

Read the worked answer

Several unknowns could shift the balance:

  • Flood depth and duration, not just frequency. Shallow, brief flooding is manageable; deep, long flooding is not.
  • Sea-level rise projections for the site, and storm surge heights. If surge regularly covers 1.5 m, the marsh is unsuitable.
  • Ground conditions on the marsh (peat or soft mud) and on the ridge (rock depth).
  • Cost of the ridge access road and of foundations, against the budget.
  • Whether the marsh currently stores floodwater for the town; losing it could worsen flooding elsewhere.
  • Population growth and school capacity.

If surge risk is high or the marsh stores floodwater, the recommendation should move firmly to the ridge and a smaller housing target, with the marsh kept as open space.