Farmer Sidorau leases 15 hectares of agricultural land from a local executive committee for 10 years to grow grain. After two years of losses, he wants to convert 5 hectares to a small agrotourism site with cabins. The lease prohibits changes to the designated purpose without the lessor's consent. The executive committee refuses, citing the land's agricultural classification. Sidorau argues the cabins occupy only 0.3 hectares and the rest remains agricultural. He has already built two cabins without approval. Advocate L. is consulted on whether the refusal can be challenged and what liability Sidorau faces for the unapproved construction.

1. Assess the legal position on changing the designated purpose of the leased agricultural land.

Read the worked answer

The designated purpose of agricultural land is a legal characteristic tied to the land category, not merely to the area actually built on. Changing it requires a decision by the competent authority and, where the lease conditions require it, the lessor's consent. Sidorau's argument that only 0.3 hectares is affected misses the point: the plot's classification governs permissible use, and agrotourism is not automatically an agricultural use on such land. Advocate L. should advise that the refusal is likely lawful unless Sidorau can show the executive committee acted outside its competence or failed to follow procedure. The realistic path is to apply formally for a change of purpose or to seek a separate plot designated for agrotourism, not to build first and argue later.

2. What are the consequences of the unapproved construction, and how should Advocate L. mitigate them?

Read the worked answer

Unapproved construction on land whose designated purpose does not permit it exposes Sidorau to administrative liability and to a demand to remove the structures or restore the land. The structures may be treated as unauthorized and subject to demolition at the owner's expense. Advocate L. should advise immediate suspension of further construction, document the current state with photographs and a survey, and file a regularization application if any procedure allows it. Simultaneously, prepare for the possibility of an administrative case by gathering evidence of good faith (the lease, the losses, the intent to diversify). Negotiating with the executive committee for a compliant alternative use or a plot exchange is often cheaper than litigation, and any appeal of the refusal must be filed within the statutory period.