The Landfill That Will Not Take the Debris

CA Asbestos Abatement · Put your knowledge to work in context.

All case studies

The Landfill That Will Not Take the Debris

A contractor has finished removing 8,000 pounds of asbestos-containing floor tile and mastic from a retail renovation. The debris is bagged in 6-mil polyethylene bags inside labeled fiber drums, wetted, and sealed. The contractor's usual landfill has stopped accepting asbestos waste because of a permit issue, and the only alternative within 200 miles is a municipal solid waste landfill that says it can take the material if it is 'non-friable and properly bagged.' The project manager wants to load the drums onto an uncovered flatbed, tarp them, and haul them to the municipal landfill the next morning to avoid storage costs. A worker asks whether the tile is actually non-friable after removal, since some pieces broke during lifting.

1. Evaluate the waste classification and whether the municipal landfill is an acceptable destination.

Read the worked answer

The classification cannot be assumed from the original material. Floor tile and mastic are typically non-friable in place, but removal can fracture the tile, and broken pieces with exposed mastic may be friable or may become friable under handling. The worker's observation is relevant: the load should be assessed for condition, and if significant breakage occurred, the waste should be managed as friable asbestos-containing waste. The generator also needs to confirm the waste is not a characteristic hazardous waste and that the landfill's acceptance is consistent with its permit and the applicable federal and state requirements for asbestos-containing waste.

The municipal landfill's statement that it can take 'non-friable and properly bagged' material is not sufficient by itself. The contractor should obtain written acceptance criteria, confirm the landfill is authorized to receive the waste, and verify packaging and labeling meet the transport requirements. If the material is friable or condition is uncertain, the load should go to a facility permitted to accept friable asbestos waste. Choosing a destination based on convenience rather than permit authority is a violation risk.

2. Assess the proposed transport method and specify what must change before the load leaves the site.

Read the worked answer

An uncovered flatbed with a tarp is not adequate for asbestos-containing waste. The waste must be packaged in leak-tight containers, labeled with the required asbestos warning, and secured so it cannot shift, tear, or release dust during transport. Drums should be closed, and bags inside drums should be intact; if a bag is torn, it should be overbagged or the drum resealed. The vehicle should have a closed cargo area or the containers should be loaded so that they are protected from weather and abrasion, and the tarp should be intact and secured, not a substitute for closed containers.

Before departure, the contractor should verify labeling, prepare shipping records identifying the waste and destination, confirm the driver is informed of the load, and ensure the receiving facility has agreed to accept it. If any container is compromised, it should be repackaged before loading. The project manager's plan to save storage costs by rushing the load is exactly the circumstance in which packaging and paperwork failures occur.

3. The project manager proposes storing the drums outdoors behind the building for two weeks until the usual landfill reopens. Evaluate this option and the recordkeeping obligations.

Read the worked answer

Outdoor storage for two weeks is acceptable only if the containers are closed, labeled, protected from weather and physical damage, and secured from unauthorized access, and if the storage is consistent with local requirements and the site's stormwater and waste-management obligations. Drums should be on a stable surface, not in a drainage path, and inspected periodically for tears or leakage. If the containers are compromised, the material must be repackaged promptly. The contractor should also confirm that the site's lease or permit allows temporary accumulation of regulated waste.

The recordkeeping obligations include the waste shipment records or manifests identifying the waste, quantity, and destination; the landfill's written acceptance; the chain-of-custody for the waste; and the project's abatement and clearance records. These should be retained per the applicable period and made available on request. Storing to await a permitted facility is preferable to misrouting the load to an unauthorized landfill, provided the storage is managed and documented.