A public-works memo about repainting a bridge states: “The original 18-month schedule assumed two crews working in parallel. The council has funded only one crew. The contractor's revised best case of 14 months assumes favorable weather and no lane-closure delays; it is not a like-for-like comparison with the original figure. With one crew and normal weather, the realistic schedule is 26 months.” A council member cites the 14-month figure as evidence that the project is still close to the original 18-month plan. The memo also says the 26-month figure already includes normal weather delays but not major structural repairs.

1. Why is comparing the contractor's 14-month figure directly with the original 18-month figure misleading?

Read the worked answer

The two numbers are built on different assumptions. The 18-month figure assumed two crews; the 14-month figure assumes one crew but also assumes favorable weather and no lane-closure delays. Those are opposite kinds of changes: fewer workers tends to lengthen the job, while favorable conditions tend to shorten it. Comparing 14 months to 18 months therefore mixes a staffing reduction with optimistic weather and access assumptions. The memo's phrase “not a like-for-like comparison” means the numbers were not produced under the same conditions, so their apparent closeness does not show that the project is near the original plan.

2. Which figure should be used for realistic planning, and what would make the contractor's 14-month figure genuinely comparable to the original 18-month figure?

Read the worked answer

For realistic planning, use the 26-month figure: it reflects the funded one-crew staffing and normal weather. The 14-month figure is a best case under favorable weather and no lane-closure delays, so it is not a safe basis for a schedule commitment.

To make the 14-month figure comparable to the original 18-month figure, it would need to use the same crew assumption and the same weather/access assumptions. For example, the memo would need a one-crew, normal-weather estimate, or a two-crew estimate under the same favorable conditions used for the 14-month best case. Without matching those conditions, the comparison is not valid.

3. What does the memo's statement that the 26-month figure excludes major structural repairs imply about using that figure?

Read the worked answer

It means 26 months is a planning estimate for repainting under normal conditions, not a guarantee that covers every possible discovery. If major structural repairs are found, the schedule could extend beyond 26 months. A careful reader should treat 26 months as the realistic base case, while recognizing that the estimate has a stated scope limit. The memo is separating normal weather delays, which are included, from major structural repairs, which are not. That distinction matters because the council should not later claim the memo promised 26 months even if structural work is added.