Capital Rationing Under a Bond Covenant: MRI, EHR, and a Surgeon-Led ASC Joint Venture
Riverton Health is a three-hospital, 480-bed system with $640M net revenue, $38.0M EBITDA, 96 days cash on hand, and annual debt service of $14.6M - 2.60x coverage against a 2.20x bond covenant. The board has approved $45M of FY2026 capital spending, but $24M is already committed to routine replacement and IT maintenance, leaving $21M of discretionary funds. Three requests compete: (1) replace the flagship's 12-year-old MRI for $3.6M; rising rescan rates and a growing backlog are putting outpatient imaging volume at risk; (2) fund the system's 60% equity in a $24M ambulatory surgery center joint venture with 18 orthopedic and GI surgeons - $14.4M plus a $5M construction contingency; (3) a $6.0M EHR upgrade. The surgeons currently perform 40% of their outpatient cases at a competing hospital. A $15M, 10-year taxable loan at 5.0% is available. Medicare Advantage is now 46% of Medicare volume, and site-neutral payment remains a live risk for the ASC.
1. Rank the three requests and show the covenant math that constrains your answer. What do you fund, and how?
Read the worked answer
Covenant math first.
- Annual payment on $15M at 5.0% over 10 years: $15M × 0.12950 = $1.94M
- New debt service: $14.6M + $1.94M = $16.54M
- Resulting coverage: $38.0M / $16.54M = 2.30x versus a 2.20x covenant
- Covenant EBITDA floor: 2.20 × $16.54M = $36.4M
So borrowing the full $15M leaves only $1.6M of EBITDA headroom (4.2%) at a time when MA penetration is rising and site-neutral cuts are pending. That is not a cushion; it is a coin flip.
Ranking.
- MRI - fund, $3.6M from operating cash. Highest certainty, smallest check, protects an existing revenue stream, and the demand is already visible in the rescan and backlog data. No debt required.
- EHR upgrade - fund, $6.0M, phased across two fiscal years if needed. Deferral risk is security, regulatory, and revenue-cycle disruption, which are harder to recover from than a delayed project. Phase to protect liquidity.
- ASC - do not fund as proposed. $19.4M exceeds the remaining $11.4M of discretionary capital and, under a $15M loan, consumes the entire covenant cushion.
How to keep the ASC alive. Restructure rather than decline. Reduce the system's equity to 51% or lower; bring in a developer or an ASC operating partner for the real estate and fit-out; contribute land or an existing building instead of cash; or stage the commitment so the second tranche is triggered by volume milestones. The surgeons' 40% outmigration is a real threat, but a covenant breach is a larger one - and a breach raises the cost of every future dollar the system borrows.
2. Build the net-impact case for the ASC. Do not just calculate the project's standalone return - show the system-level effect, including what happens if Riverton does nothing.
Read the worked answer
Standalone pro forma (illustrative). Assume the JV captures 6,300 of the surgeons' 9,000 outpatient cases at $2,400 net revenue per case, with 62% operating expense:
- Revenue: 6,300 × $2,400 = $15.1M
- EBITDA: 38% = $5.7M
- System's 60% share: $3.4M per year; payback on $14.4M ≈ 4.2 years
Standalone, that looks acceptable. The system-level view is not.
Cannibalization. About 3,800 of those 6,300 cases are currently performed in Riverton's hospital outpatient departments, where contribution per case is roughly $1,650. Shifting them to the ASC forgoes 3,800 × $1,650 = $6.3M of hospital contribution. Netting the system's $3.4M ASC share against that gives −$2.9M in year one. Converting hospital outpatient cases to a lower-paying ASC is margin-dilutive in the near term; the justification has to come from elsewhere.
The "do nothing" case is also not zero. If the surgeons move their remaining 5,400 cases to the competitor, Riverton loses 5,400 × $1,650 = $8.9M of annual contribution, plus the associated imaging, pathology, and anesthesia volume. So the decision is not "$14.4M for $3.4M" - it is choosing between a $2.9M dilution and an $8.9M loss.
Implication. The ASC is defensible as market defense, but only at a lower capital commitment and with a site-neutral sensitivity built into the model. If Medicare converts those cases to the lower site-neutral rate, the ASC EBITDA line falls further and the dilution widens. Underwrite it as retention, and negotiate a 51% or below equity position and a staged funding schedule that ties the second tranche to verified case migration.
3. What financial policy would you recommend the board adopt so that this conversation does not recur every budget cycle?
Read the worked answer
Adopt a written capital allocation and debt policy with explicit triggers, so the ranking is a rule applied prospectively rather than an argument relitigated each year.
Financial thresholds.
- Coverage floor of 2.35x for any transaction that adds debt, roughly 0.15x above the covenant, which preserves about $2.5M of EBITDA headroom. If a request cannot clear 2.35x, it requires a board supermajority and a written mitigation plan.
- Days cash on hand floor of 90; no project may take the pro forma below it.
- Discretionary capital envelope defined annually as cash from operations minus routine replacement, with the definition agreed in advance so the envelope is not renegotiated mid-year.
Ranking criteria, weighted. Strategic necessity and revenue protection (40%), return and payback (25%), risk including payer and site-neutral exposure (20%), and mission/access (15%). Score every request against the same rubric and publish the scores to the board.
Structural rules.
- Projects above $10M require a standalone net system-impact model that includes cannibalization, not just project-level return.
- Any joint venture must carry a staged funding schedule with volume triggers and a defined exit mechanism.
- A payer-concentration trigger: if MA exceeds 50% of Medicare volume or any single payer's rate cut exceeds 2%, the capital plan is re-run before the next commitment.
Reporting. A quarterly capital dashboard showing coverage, days cash, active project spend versus authorization, and realized versus projected returns. The most common failure is not a bad ranking; it is approving a project on a pro forma that is never revisited. Require a post-completion audit at 12 and 24 months, with the results reported to the finance committee.