Trade-Specific Technical Knowledge and Theory

Trade-Specific Technical Knowledge and Theory

The theory paper asks why your trade works, not only how to repeat a gesture. Whatever your speciality - masonry, joinery, motor mechanics, electrical installation, refrigeration, tailoring, hairdressing or catering - the examiner wants correct trade vocabulary, material choices you can justify, and procedures described in the right order with quantities and units.

What is tested

  • Vocabulary and definitions of tools, materials, components and common defects, written in the language of the paper.
  • Material properties: hardness, conductivity, elasticity, water absorption, grain direction, heat resistance, shrinkage.
  • Sequences: operations whose order cannot be reversed without damage (curing before loading, cooling before measuring, priming before painting).
  • Quality criteria: dimensions, tolerances, finish, drying and curing times, standard ratios and dosages.

Core rules

  1. Name things with the exact technical term, not workshop slang, and give the unit after every number.
  2. Justify a material by its properties: "aluminium because it resists outdoor corrosion", not "because we always use it".
  3. Say which check proves the work is correct, and with which instrument.
  4. When a result depends on a prior condition, state the condition - a floor is tiled on a cured, dust-free screed, not on a fresh one.

Worked example

A concrete slab measures 3.5 m by 4 m and is 8 cm thick. The dosage is 350 kg of cement per m³, cement is sold in 50 kg bags, and 5 % is added for waste. How many bags are needed?

Volume = 3.5 × 4 × 0.08 = 1.12 m³ (8 cm converted to 0.08 m). Cement = 1.12 × 350 = 392 kg. With waste: 392 × 1.05 = 411.6 kg. Bags = 411.6 ÷ 50 = 8.23, so buy 9 bags. The reasoning matters as much as the figure: you round up because a bag cannot be bought in fractions and a lean mix weakens the slab.

Traps that cost marks

  • Mixing millimetres, centimetres and metres inside one calculation.
  • Confusing nominal (sawn) and finished (planed) timber sizes, so the finished piece comes out undersize.
  • Forgetting waste, overlap, jointing or shrinkage allowances.
  • Writing a bare number with no unit and no statement of rounding.
  • Answering "the usual way" instead of describing the expected sequence step by step.