Ridgeline Equipment builds pump assemblies in Chicago and ships 25,000 kg per month to a Dallas distribution centre. Each kilogram of finished product carries $60 of value, and finance applies a 22% annual holding cost. Current practice is LTL: $0.28/kg plus about $450 a month in accessorials (redelivery, detention), 4-day transit, 92% on-time. Three alternatives are on the table: (a) full truckload, two 12,500 kg shipments a month at $3,900 each, 2-day transit, 99% on-time; (b) intermodal, three 8,334 kg lots at $0.14/kg plus $600 drayage per lot, 5-day transit, 84% on-time; (c) a 3PL pool-distribution contract at $0.31/kg, 3-day transit, 97% on-time. Dallas holds one week of inbound safety stock today and could cut it to three days at 99% inbound reliability, or would need two weeks at 84%. Dallas also charges back $750 per inbound-late delivery, and about 10 a month are charged back today.

1. Build a monthly total-cost comparison of the four options and make a recommendation.

Read the worked answer

Four cost lines: freight, pipeline inventory, DC safety stock, and late-delivery chargebacks. Monthly holding rate = 22%/12 = 1.833%. Pipeline inventory = 25,000 kg x (transit days / 30) x $60.

Line LTL FTL Intermodal 3PL pool
Freight $7,450 $7,800 $5,300 $7,750
Pipeline inventory 3,333 kg = $200,000 -> $3,667 1,667 kg = $100,000 -> $1,833 4,167 kg = $250,000 -> $4,583 2,500 kg = $150,000 -> $2,750
DC safety stock 1 wk = $346,154 -> $6,346 3 d = $150,000 -> $2,750 2 wk = $692,308 -> $12,692 5 d = $250,000 -> $4,583
Chargebacks $7,500 $750 $15,000 $3,000
Total / month $24,963 $13,133 $37,575 $18,083

Recommendation: full truckload, at roughly $11,800 a month less than the status quo - about $142k a year. Note what the table shows: intermodal has the lowest rate per kilogram by a wide margin ($0.14 vs $0.28) and is the worst option on total cost, because 84% reliability has to be paid for twice, once in inventory and once in chargebacks. Reliability, not rate, is the driver.

State the assumptions in your answer: 12,500 kg is a full truck for this product, the safety-stock estimates are proportional approximations, and the chargeback frequency scales with on-time performance. Validate all three with three months of actual data before committing.

2. What would change the recommendation, and how would you de-risk the switch?

Read the worked answer

What would change it:

  • Volume. Below roughly 7,000 kg a month, FTL becomes one truck every three-plus weeks, which stretches the order cycle and forces more DC inventory - at that point LTL or the 3PL pool wins. Build the break-even volume explicitly.
  • Rate durability. Two loads a month is a thin relationship; the $3,900 rate may not survive a tight capacity market, and a carrier can deprioritise a small shipper. Contract the lane with a fuel surcharge formula and a capacity commitment, or run a mini-bid with a primary and a backup carrier.
  • Concentration. Two shipments a month means one accident or one missed pick-up removes half a month of supply. That is why the answer is not 'FTL only'.
  • Service expectation change. If Dallas customers move to smaller, more frequent orders, the whole analysis shifts.

De-risking:

  • Run a three-month pilot of FTL on the lane while keeping LTL active as a fallback, and measure actual on-time and chargeback rates rather than trusting the quoted 99%.
  • Contract a backup carrier at a spot rate for surge weeks, and keep a small expedite budget rather than a large buffer.
  • Cut the Dallas safety stock only after the new transit performance is demonstrated for eight to ten weeks - releasing stock on a promise is how the switch fails.
  • Do not let the intermodal option disappear entirely; keep a quarterly rate check, because if rail reliability improves or a customer imposes a hard carbon requirement, the analysis moves.

3. The largest customer now demands a 25% carbon cut in the inbound supply chain. Does that change the modal choice?

Read the worked answer

Quantify before you switch modes, because the instinct to move freight to rail is often right in principle and trivial in magnitude here.

Rough numbers: 25,000 kg x about 1,450 km = roughly 36,000 tonne-km a month. Truck freight at about 60-65 g CO2 per tonne-km gives roughly 2.2 t CO2 a month; rail at about 20-25 g gives roughly 0.8 t. The modal difference is about 1.4 t a month, under 20 t a year - small next to the embodied carbon of the product itself.

Weigh three things:

  1. Mode is one lever; utilisation is another. Two full truckloads a month already run at good utilisation, so there is little empty-mile waste to remove on this lane - which is itself a carbon argument for FTL over LTL, where partial loads and rehandling add emissions per tonne shipped.
  2. Inventory is a carbon cost too. Intermodal would require 11,500 kg of extra safety stock versus 2,500 kg under FTL; that is production, packaging and warehousing emissions incurred to protect against a slow mode. Counting only tailpipe emissions would flatter intermodal.
  3. Disruption emissions dominate. A single air-freight expedite of pump assemblies can exceed a year of regular inbound trucking. Reliability is a decarbonisation strategy, not just a service one.

Recommendation: keep FTL, and answer the customer with a Scope 3 methodology - tonne-km, carrier-specific emission factors, a data-quality statement - plus the bigger levers: carrier emissions reporting as a contract clause, backhaul and consolidation opportunities, and packaging cube reduction. Set the 25% target against a measured baseline rather than promising a modal shift you cannot substantiate.