Shift-Change Meltdown at a 911 Center

ArcGIS Enterprise Admin (EAEP) · Put your knowledge to work in context.

All case studies

Shift-Change Meltdown at a 911 Center

A regional 911 center runs a three-machine ArcGIS Server site (16 vCPU, 64 GB RAM each), a single-machine portal, and relational plus tile cache data stores. The site hosts 120 services, including two geoprocessing services that build drive-time polygons from about 6,000 points and take roughly 7 minutes each; a Python script calls one of them every 15 minutes around the clock. A situational-awareness dashboard is opened by about 4,000 concurrent viewers at the 07:00 and 15:00 shift changes. At both peaks, map response time climbs from 1.2 s to 22 s, ArcSOC processes on one machine pin the CPU at 100%, and the portal stops responding for three to four minutes. Server logs show "Request timed out" and the portal logs show Java heap errors. Disk usage on all three machines is over 85% because server log level was set to DEBUG five months ago by a vendor. Nobody monitors anything beyond a weekly manual check of the Services Directory.

1. Separate the symptoms into distinct faults and give a triage order with the evidence you would collect first.

Read the worked answer

There are at least three independent faults here, and treating them as one will produce a change that fixes nothing.

Fault 1 - portal JVM exhaustion. Java heap errors plus three to four minutes of unresponsiveness is classic GC thrash: the JVM spends all its time collecting and none serving. Concurrent logins and dashboard token traffic spike at shift change. Evidence: portal logs, a heap histogram (jmap/jstack) during a peak, and the configured heap size versus the machine's RAM. Fix direction: right-size the heap (the default is small relative to what a portal does), reduce cost per request by disabling unused features and clearing stale statistics, and consider a second portal node behind the load balancer.

Fault 2 - CPU saturation on one GIS machine. The 15-minute geoprocessing job at 7 minutes per run means the job overlaps itself and the shift change. By default a GP service shares the SOC pool with map services, so a heavy synchronous job starves rendering. That only one machine pins at 100% also indicates the requests are not being evenly distributed. Evidence: per-machine service instance counts, the GP service's instance settings, and the timing of the script relative to 07:00 and 15:00.

Fault 3 - storage and observability debt. DEBUG logging at 85% disk is a latent outage; a full log volume takes down the portal or server. And with no monitoring, the team cannot establish a baseline.

Triage order: stop the bleeding on disk first (it is the cheapest action and the most likely to cause a hard failure), then portal heap, then service instance settings, then monitoring.

2. Specify the configuration changes you would make to the geoprocessing service and the site, and justify each.

Read the worked answer

Geoprocessing service:

  • Set isolation to dedicated so the GP service gets its own SOC processes instead of competing with map services in the shared pool. This is the single highest-impact change: it stops the outage from being a site-wide event.
  • Set max instances low (often 1–2 for a 7-minute job) to prevent the scheduled call from stacking copies of itself when a run overruns.
  • Set a maximum execution time on the service so a runaway job cannot occupy a slot for hours.

The scheduled job:

  • Move it off the shift-change windows, or reduce frequency; every 15 minutes around the clock is unnecessary for a 7-minute analysis. Consider precomputing results and serving them as a cached layer for the dashboard, which is the real fix: dashboards at shift change do not need live drive-time computation.

The site:

  • Rebalance machine assignment. Watch whether one machine receives disproportionate requests; the load balancer, not the server, usually causes this.
  • Review max instance counts and timeouts per service for map services too; an unbounded max instance count turns a traffic spike into a memory event.
  • Determine whether the dashboard consumes cached tiles or dynamic layers. If dynamic, convert suitable layers to cached tiles; that alone removes most of the CPU load at 4,000 viewers.

Justification to give stakeholders: dedicated isolation plus a cap converts a site-wide outage into a degraded single service; moving the job and caching the dashboard addresses the load itself; both are reversible and require no new hardware.

3. Design the monitoring and maintenance regime going forward, including what to do about the DEBUG logging the vendor wants kept.

Read the worked answer

Logging. Set server log level back to WARNING and cap log retention. A vendor who wants DEBUG should get it scoped: raise the level on a single service (or for a defined troubleshooting window), capture what is needed, and revert. Persisting DEBUG indefinitely is not observability - the volume destroys signal, fills disks, and degrades performance. Add central log collection with retention that is enforced automatically, and alert on disk usage above 75%.

Monitoring. Without a baseline, every incident is argued from anecdote. Deploy ArcGIS Monitor (or an equivalent) and alert on:

  • per-service average and 95th-percentile response time, with thresholds set from a known-good baseline rather than guesses;
  • service instance saturation (busy instances versus max instances) per service and per machine;
  • error rates in server and portal logs, particularly 498 and timeout patterns;
  • portal JVM heap usage and GC time;
  • disk, CPU, and memory on every machine, plus data store health and backup status;
  • an external uptime check that performs a real transaction (portal sign-in to service draw), not a port test.

Maintenance rhythm. Weekly: review dashboards, prune stale items, verify backups restorable. Monthly: patch cycle, review service instance settings against actual usage, audit log levels. Quarterly: failover drill, capacity review against known peaks such as the shift change, and a restore test of at least one data store backup.

Capacity note. A single portal machine serving 4,000 concurrent viewers at shift change is the structural risk. The heap tuning buys headroom; a second portal node behind the load balancer is the durable fix and should be in the next budget cycle.