Building a Single Service Management Model After a Hospital Merger
Two regional hospitals merge into a 6,500-staff group with three main sites and 24/7 clinical operations. Each hospital has its own service desk, incident process and CMDB; monthly ticket volume is 2,800. The merger target is 18% synergy in 18 months, and the board wants a single service management model within 90 days. Clinical systems include electronic prescribing, imaging and a patient portal. A recent outage showed that the on-call rota was not shared between sites, and it took 47 minutes to find the right engineer. The two CIOs have different governance styles: one uses a weekly change board, the other delegates to platform teams. Clinicians fear that standardization will break local workflows; the integration lead wants to centralize everything quickly. A regulator requires evidence of clinical risk control and incident reporting.
1. How should the merged group apply the VeriSM model to create a single service management model without breaking clinical workflows?
Read the worked answer
Use the VeriSM model as a sequence of decisions, not a documentation exercise. In Define, agree the shared service outcomes: safe patient care, clinical availability, incident response and regulatory evidence. In Produce, design a minimum viable model: one incident process, one on-call directory, common severity levels, shared major incident command and a single service catalogue. In Provide, deliver with federated execution: local clinical teams keep their workflows and super-users, while central teams own standards and tooling. In Respond, use incidents, feedback and audit findings to improve the model.
Do not centralize everything in 90 days. The 47-minute delay to find the right engineer is a mesh failure in resources and information, so fix the on-call directory and shared contact data first. Standardize what affects safety and coordination; leave local clinical configuration to local owners. Run one pilot on imaging and one on the patient portal before scaling. The board should receive a 90-day milestone plan: shared incident command in 30 days, on-call directory in 45, common catalogue in 90. This respects clinical variation while creating a single operating model.
2. What should be centralized, federated or left local in the management mesh, and why?
Read the worked answer
Centralize identity and access, the on-call directory, major incident command, common monitoring, vendor contracts and CMDB standards. These are coordination and safety assets; fragmentation caused the 47-minute delay. Federate clinical application ownership, change planning for clinical systems and local training, with central guardrails. Leave local workflow configuration, super-user support and site-specific escalation to the sites, because clinicians understand patient flow.
The reasoning is that the mesh should place decision rights where knowledge and risk sit. Centralizing everything would break clinical workflows and create a new bottleneck. Leaving everything local would repeat the outage. Use a RACI for each service and a service taxonomy: group-wide, shared, site-specific. For clinical systems, a clinical safety officer should have veto authority. Publish the model and test it with a tabletop outage across two sites. Success is not a single org chart; it is a shared on-call list, one incident process and local ownership of clinical configuration. Review the split after 90 days using incident data.
3. How should governance handle the 90-day board deadline and the regulator requirement?
Read the worked answer
Separate the board deadline from the operating model. The board can approve a 90-day direction, guardrails and a milestone plan; it should not approve every local workflow. Set up a joint governance group with the two CIOs, a clinical safety officer, the integration lead and a regulator liaison. Define decision rights: group-wide standards and risk appetite at the group; clinical configuration at the sites; incident command under the group major incident process. Build regulatory evidence into the process: incident reporting, clinical risk assessments, audit logs and review records.
The 90-day deadline should deliver a minimum viable model, not full standardization. Sequence: shared incident command and on-call directory first, common severity and reporting second, catalogue and CMDB standards third. Report to the board monthly on three outcomes: time to restore clinical service, cross-site incident handoff and regulatory evidence completeness. If the regulator requires evidence of clinical risk control, do not wait for the new tool; use the existing systems to produce a manual evidence pack. Governance succeeds when the board sees control through outcomes and exceptions, while clinicians keep enough local authority to protect patient care.