Engineering Economics
Engineering Economics
The FE Mechanical engineering economics items test time value of money, equivalence, project evaluation, depreciation, taxes, and inflation. Most problems reduce to converting cash flows to a common point in time and comparing alternatives on a consistent basis.
Core rules and concepts
- Single payment: F = P(1 + i)^n and P = F(1 + i)^(-n).
- Uniform series: (F/A, i, n) = ((1 + i)^n - 1)/i; (A/F, i, n) = i/((1 + i)^n - 1); (P/A, i, n) = ((1 + i)^n - 1)/(i(1 + i)^n); (A/P, i, n) = i(1 + i)^n/((1 + i)^n - 1).
- Effective annual rate for nominal rate r compounded m times per year: i_eff = (1 + r/m)^m - 1. For continuous compounding, i_eff = e^r - 1.
- Net present value: NPV = Σ CF_t/(1 + i)^t. For an independent project, accept if NPV > 0. IRR is the i that makes NPV = 0.
- For mutually exclusive alternatives, use incremental analysis or compare NPV; ranking by IRR alone can mislead.
- Depreciation: straight-line annual amount = (P - S)/n. MACRS is accelerated and uses a half-year convention for the first year.
- Inflation: (1 + i_nominal) = (1 + i_real)(1 + f).
Worked example
A machine costs $10,000, saves $3,000 per year for 5 years, and has a $1,000 salvage value. MARR is 10%. Compute NPV = -10,000 + 3,000(P/A, 10%, 5) + 1,000(P/F, 10%, 5). Using (P/A, 10%, 5) = 3.7908 and (P/F, 10%, 5) = 0.6209: NPV = -10,000 + 11,372.4 + 620.9 = $1,993.3. Since NPV is positive, the machine is economically justified at a 10% MARR.
Traps that cost marks
- Treating an annuity due as an ordinary annuity; begin-of-period cash flows need an extra (1 + i) factor.
- Mixing nominal and effective interest rates.
- Including sunk costs in a decision.
- Omitting salvage value or giving it the wrong sign.
- Assuming MACRS equals straight-line depreciation.
- Choosing the higher IRR when alternatives differ in scale; use incremental NPV.