A Critical Supplier's Operator-Error 8D, a Deviation Request, and a Skip-Lot Plan
Bracken Aerospace buys machined aluminium actuator housings from a single source, Precision Turned Components (PTC). The drawing specifies a bore diameter of 25.000 ± 0.020 mm and true position of 0.05 mm. Incoming inspection uses a skip-lot plan: five pieces per lot, and three lots skipped after ten consecutive conforming lots. PTC has shipped 14 consecutive conforming lots, so the last three were skipped. The current lot, L-2291, failed: 2 of 5 pieces were out of tolerance on bore diameter (25.026 mm and 25.031 mm) and one had true position of 0.08 mm. PTC's 8D classifies the cause as 'operator error - new operator on night shift', with corrective action 'retrain operator, add checklist', and asks Bracken to accept a 200-piece deviation to ship the lot as-is. PTC also asks to be approved for a new housing part number and cites a 99.2% on-time delivery record. Assembly has three days of housings left, and Bracken's customer requires full traceability plus a first article inspection for every new part.
1. Evaluate PTC's 8D. Which elements are missing, and what would you require before accepting it?
Read the worked answer
'Operator error' is a stopping point, not a root cause. ISO 9001:2015 clause 10.2 expects reaction, evaluation of the need for action to eliminate the cause, implementation, and review of effectiveness. Retraining plus a checklist is containment and detection, not cause elimination.
Missing elements.
- Why the operator was there. A new night-shift operator on a critical bore operation implies a competency/qualification system failure. Who authorized assignment, what training record existed, how was competence verified?
- Escape analysis. Bore oversize of 0.026-0.031 mm should be caught by PTC's final inspection if it gauges 100% or by in-process SPC. Why did it reach Bracken? The two-part answer is normally detection (gauging frequency, gauge capability) and process (tool wear, thermal drift on night shift).
- Measurement system. Was the bore measured with a gauge with acceptable GR&R? Confirm before attributing parts to a person.
- Scope. One operator, one shift, or systemic? Data from other lots and shifts either supports or kills the hypothesis.
- Effectiveness verification. Three consecutive lots with capability data, not a signed retraining sheet.
Decision. Reject the 8D as incomplete; return it with the specific questions. Accept the interim containment (retrain, checklist) as temporary while root cause work continues, and require a revised 8D with data within a stated period. A supplier's on-time delivery record is irrelevant to whether a corrective action closes.
2. Should Bracken approve the 200-piece deviation? Work through the decision and who owns it.
Read the worked answer
Start with the characteristic, not the quantity. The bore is an actuator housing fit; oversize bore reduces interference or changes clearance, and true position affects assembly alignment. That is form, fit and function territory.
Decision logic.
- Is the drawing customer-controlled? Bracken's customer requires full traceability and FAI for new parts, which suggests a customer-owned design. Where a deviation affects a customer-specified or key characteristic, Bracken normally cannot self-approve; the request goes to the customer with supporting analysis.
- What analysis supports use-as-is? Worst-case fit and clearance calculation using 25.031 mm and 0.08 mm true position, plus functional test data on parts at the extremes. A statement that the assembly is 'non-critical' is not analysis.
- What happens if it fails in service? An actuator housing with an out-of-spec fit can produce binding, lost motion, or premature wear, with warranty and safety implications.
- Alternatives first. 100% sort and gauge the lot, segregate conforming pieces, and quantify how many are truly usable; check whether rework is technically feasible and approved. Deviation should be the last option, not the first.
Supplier's stock position. Three days of cover is a supply continuity problem, not a quality justification. In parallel, push for expedited replacement, authorize overtime at an approved alternative source, and give the customer a recovery plan.
Who owns the decision. Material review with quality, engineering and the customer's supplier quality function where the characteristic is customer-designated. The quality function holds a veto; commercial pressure does not vote.
3. What is your response to PTC's request for approval on the new housing part, and how should the skip-lot plan be adjusted now?
Read the worked answer
New part approval. On-time delivery is a delivery metric and does not substitute for process capability evidence. Require, before approval:
- Process FMEA and control plan for the new part, plus a process flow diagram.
- MSA for each inspection method, and capability studies on critical characteristics from a stable process, typically Ppk at or above 1.67 for a new part on safety-related features.
- Full first article inspection to the customer's requirement, with ballooned drawing and material/process certificates.
- A closed, verified corrective action history on the existing part, not a plan.
Approval should be conditional and staged: trial lots with first-article and capability data, then production approval after demonstrated performance.
Skip-lot. The premise of skip-lot is a demonstrated stable process with a quality history. Five pieces revealing two out-of-tolerance bores is a high defect rate in that sample, which invalidates the premise. Therefore:
- Return to tightened inspection immediately - increased sample, or 100% verification of critical characteristics for a defined number of lots.
- Assess the three skipped lots retrospectively: pull retained samples or returned stock and check the same characteristics. Skipped lots are unverified, not known good.
- Define exit criteria in writing: for example, ten consecutive conforming lots, 100% critical-characteristic verification, and verified corrective action effectiveness, with the supplier quality function approving the return to normal inspection.
- Treat this as a supplier risk rating change and record it; the deviation request should not influence the inspection decision.