GSL Interpretation of Deeds & Statutes study materials
GSL Interpretation of Deeds & Statutes study resources

The Glamping Pods and the Meaning of 'Caravan'

GSL Interpretation of Deeds & Statutes · Put your knowledge to work in context.

All case studies

The Glamping Pods and the Meaning of 'Caravan'

Your client, Fawley Farm Leisure Ltd, has converted a 12-acre field in Devon into a 'glamping' site. It has installed ten timber pods, each 6m by 3m, resting on steel skids. Each pod contains a double bed, a wood-burning stove, a small sink and a compost toilet. The pods are towed into position by tractor; they have no foundations, no wheels and no tow bar of their own. The local planning authority has served an enforcement notice alleging a breach of planning control by 'the stationing of caravans for human habitation' and requiring removal of all ten pods within 28 days. The client's director says the pods are 'buildings, not caravans' and points out that the site has never been used by touring caravans. The authority relies on the Caravan Sites Act 1968, s.13, and on its own supplementary planning document, which states that 'glamping pods of the type described are caravans'. The client has 14 days to appeal.

1. Advise whether the pods fall within the definition of 'caravan' in s.13 of the Caravan Sites Act 1968. Apply the literal rule, the golden rule and the purposive approach, and explain which is most likely to succeed.

Read the worked answer

Section 13(1) of the Caravan Sites Act 1968 defines a caravan as a structure designed or adapted for human habitation which is capable of being moved from one place to another (whether by being towed, or by being transported on a motor vehicle or trailer), and any motor vehicle so designed or adapted.

The pods satisfy the first limb. They contain sleeping and washing facilities and are designed for people to live in temporarily. The phrase 'designed or adapted for human habitation' does not require permanence. They satisfy the second limb. They can be towed by tractor and lifted onto a trailer, even without their own wheels or tow bar. The absence of wheels is not decisive because the statute expressly contemplates movement by being transported.

The literal rule therefore points strongly to the pods being caravans. The golden rule would only assist if the literal meaning produced an absurdity or repugnancy; here it does not. The purposive approach supports the same result: the mischief was the uncontrolled use of land for movable accommodation, and the pods are precisely that. The client's best argument is that the pods are 'buildings' because they rest on skids and are connected to services, but the statutory definition is exhaustive and broad; a structure does not cease to be movable because it is heavy. I would advise that the pods are likely to be held to be caravans, and the appeal should not be fought on that point alone.

2. The authority's supplementary planning document states that pods of this type are caravans. To what extent can the client rely on, or challenge, that document in an appeal?

Read the worked answer

A supplementary planning document is not legislation. It is a statement of the authority's planning policy, and it cannot alter the meaning of a statute. In an appeal, the inspector or court will interpret s.13 as a matter of law.

The document may be relevant as background, but its assertion is not determinative. A planning authority cannot bootstrap its own guidance into a statutory definition. Pepper v Hart [1993] AC 593 permits reference to Hansard only where the legislation is ambiguous, the statement is clear, and a minister or promoter made it. A supplementary planning document is not Hansard.

The authority's own view may be evidence of how it applies the law, but it is not a substitute for the words of the Act. The client can challenge the document's statement as a misstatement of law. If the authority has applied it as if it were law, that is an error of law and a ground of appeal. The document may still be relevant to the exercise of planning judgment, for example on whether permission should be granted, but it cannot decide the statutory question.

3. If the pods are caravans, what is the consequence for the enforcement notice and what practical steps should the client take within the 14 days?

Read the worked answer

If the pods are caravans, the enforcement notice is likely to be valid in form, but validity does not make it unappealable. The client should appeal within 14 days under s.174(2) of the Town and Country Planning Act 1990; the appeal suspends the notice.

Grounds include: (a) planning permission should be granted; (b) the matters alleged have not occurred; (c) the notice is defective. The strongest ground may be (a): a retrospective application for a caravan site licence and planning permission, with a landscaping scheme and a 10-pod limit. The client should also consider whether the site benefits from permitted development rights, though these are unlikely for a commercial glamping site.

A caravan site licence under the Caravan Sites and Control of Development Act 1960 is also required; operating without one is an offence. The 28-day compliance period is suspended by the appeal, so the immediate removal risk is managed. The client should not wait for the appeal to apply for planning permission; an application should be lodged now. A parallel application for a lawful development certificate is unlikely to succeed if the pods are caravans and no permission exists.