Flat Rack, Wrong Weight, Off-Centre Load at Berth 4

HK MBST Container Handling Test · Put your knowledge to work in context.

All case studies

Flat Rack, Wrong Weight, Off-Centre Load at Berth 4

Berth 4. A 20ft flat rack carries a used hydraulic power pack. The shipping documents declare a verified gross mass of 18,500 kg, but the terminal weighbridge records 26,940 kg for the packed unit. The cargo drawing marks the centre of gravity 0.55 m to port of the centreline and 1.3 m aft of mid-length. The power pack is held to the flat rack by two ratchet straps rated at 5 t working load each. The quay crane's load chart for a 20ft spreader at 38 m outreach gives a safe working load of 32.0 t in still air. Wind is 12 m/s, gusting 16. The planner wants the unit lifted over the live truck lane into a ground slot 60 m away; the alternative route over the water side adds nine minutes. The spreader's rotating head is serviceable; there are no taglines rigged. The flat rack's CSC plate is legible, but the corner castings at the port-aft corner show deformation and paint cracking.

1. Is the lift permissible as planned? Show the calculation and the checks you would make before authorising it.

Read the worked answer

Start from the heavier number. Until the mass is verified, plan on 26,940 kg.

  • Capacity: 26.94 t against a 32.0 t chart figure at 38 m is 84% of SWL. Inside the chart - but a chart figure assumes a centred load, still air, level ground and correct reeving. Here none of those assumptions holds, and the margin is only 5.06 t.
  • Wind: 12 m/s gusting 16, with a flat rack carrying a bulky machine and a large sail area. The chart is not a wind chart; apply the manufacturer's wind derating and the terminal's stop limit, and measure at the work front.
  • Off-centre CoG: 0.55 m off the centreline transfers load onto the port twistlocks and twists the rack; a rotating head makes attachment easier but does not restore capacity. Get the crane and spreader maker's eccentric-load allowance, or work it by load moment.
  • The flat rack itself: check its marked rating and CSC plate, and the deformed port-aft corner casting. A distorted casting may not accept the twistlock fully and can distort further under 27 t. That finding alone stops the lift until a competent person assesses it.
  • Cargo securing: two 5 t straps give about 10 t of restraint against 26.9 t of machinery. If the unit tilts on the hook, the cargo moves; the rack has a lashing plan for a reason.
  • Route: a suspended load over a live truck lane breaches the lift plan and the general duty to keep people out from under loads. The nine minutes saved is irrelevant.

Conclusion: no, not as planned. Re-weigh, verify the rack, obtain the eccentric-load allowance, re-secure the cargo, rig taglines, close the lane, and re-plan the route before any hook-up.

2. The declared VGM is 8.4 t lighter than the weighbridge figure. How do you handle that as a lifting and safety issue, not just paperwork?

Read the worked answer

Treat the discrepancy as a red flag, not a clerical correction. An 8.4 t gap on 18.5 t is roughly a 46% under-declaration.

  1. Stop the unit. Do not lift or load it on the strength of either number until it is verified.
  2. Re-weigh properly. Use the calibrated terminal weighbridge for the packed container, with the tare accounted for, and check the weighbridge calibration certificate is current. Note that weighing a container on a road vehicle introduces the vehicle's own mass and axle effects - control that or use a container weighbridge.
  3. Tell the parties. The planner, the shipping line and the shipper must know before the stow plan is fixed; a corrected VGM is required from the shipper under the SOLAS verified-gross-mass requirement, and the terminal should not load without one.
  4. Re-check capacity on the true mass - crane chart, spreader rating, the flat rack's rating, and the ground slot or stack the unit will sit in. A stack designed for 18.5 t may not accept 26.9 t.
  5. Record and escalate. Keep the weighbridge ticket, the declared VGM and the correspondence; flag a suspected mis-declaration to the line. Under-declared weight is a recurring cause of crane overloads and stack failures, so the finding should go into the terminal's safety data, not just the shipping file.

Reasoning: the declared mass drives the lift plan, the stow plan and the ship's stability. Any one of those being wrong is enough to stop the job; the safety consequence is the reason the paperwork rule exists.

3. What does the off-centre centre of gravity change about the spreader attachment and load stability, and what would you require before the lift proceeds?

Read the worked answer

What the offset does

  • Unequal twistlock loading. With the CoG 0.55 m to port, the two port twistlocks and their corner castings carry noticeably more than half the load. The crane's SWL assumes a centred load; the spreader and the rack may each need derating.
  • Rack distortion. A 20ft flat rack is stiff in the longitudinal direction and weaker against twist. An eccentric 27 t mass increases torsional deflection, which is exactly where the deformed port-aft casting is a concern.
  • Hanging attitude. The unit will not hang level: it lists and trims. That makes twistlock engagement in the ground slot harder, increases swing, and lengthens the time the load is suspended over the yard.
  • Secondary movement. If the machine is not restrained against sliding and the unit tilts, the CoG moves further out and the load can shift - a self-worsening condition.

Pre-lift requirements

  1. Written confirmation from the crane/spreader manufacturer of the permitted eccentricity, or a load-moment calculation by a competent person.
  2. The flat rack inspected and cleared, with the port-aft casting assessed and, if suspect, the unit rejected for lifting in that condition.
  3. Cargo re-secured to a documented lashing plan with adequate restraint for the real mass.
  4. Taglines from outside the fall zone, no personnel beneath, the lane closed.
  5. A trial lift of 100–200 mm, hold, and check list and trim against an agreed limit; abort if the unit lists beyond that limit.
  6. A nominated banksman with radio, and a stop authority that anyone can use.

Reasoning: the rotating head solves attachment geometry, not load distribution. The correct decision is driven by the two things nobody has yet confirmed - the true mass and the maker's eccentric-load allowance.