The 19-Day Lease and the 'To Follow' Letter

ICC PCS · Put your knowledge to work in context.

All case studies

The 19-Day Lease and the 'To Follow' Letter

A general contractor submits a permit application for a 12,400-square-foot tenant fit-out in an existing single-story shell of Type IIB construction. The shell is already sprinklered. The fit-out adds a 40-foot clear-span canopy over the customer entrance, a new rooftop packaged unit, and a 900-pound masonry screen wall around the rooftop equipment. The submittal contains architectural, mechanical, electrical, and plumbing drawings sealed by the architect and engineers of record. It does not contain the pre-engineered canopy truss design, the fire sprinkler shop drawings and hydraulic calculations, energy code compliance documentation for the rooftop unit, or structural calculations for the screen wall. The contractor's cover letter asks that the permit be issued immediately and lists all four items as 'to follow,' citing a lease commencement in 19 days and noting that a sprinkler contractor has not yet been selected. The plans examiner's supervisor is unavailable, and the contractor's expediter is pressing for a same-day decision.

1. Which of the four missing items may be accepted as deferred submittals, and what must be established before any permit is issued?

Read the worked answer

Separate the four items by what they are, not by how the letter labels them.

  • Canopy truss design and sprinkler shop drawings/hydraulics can potentially be deferred submittals, but only if the construction documents specifically identify them as deferred, list them as items, and the registered design professional in responsible charge reviews them and confirms they are consistent with the design. Each deferred item is still approved later by the building official before the covered work is installed or concealed.
  • Energy compliance documentation and structural calculations for the 900-pound screen wall are not deferred submittals. They are design documents needed to establish compliance with the energy provisions and with structural loading. Without them there is no basis for a compliance finding, and issuing the permit would approve an unevaluated design.

The correct action is a written completeness notice itemizing each deficiency, the code requirement it supports, and what an acceptable resubmittal looks like. A 'to follow' letter from a contractor is not a substitute for design documents, and schedule pressure is not a code criterion. Document the decision in the permit file and copy the expediter in writing.

2. The contractor now asks to begin interior framing because the shell is already sprinklered. How should a phased or partial authorization be evaluated?

Read the worked answer

Phased authorization is a scope decision, not a waiver of the missing documents. Work through four questions before agreeing.

  1. What exactly would be built, and does it depend on a missing item? Interior partitions may not depend on the canopy trusses; the canopy framing clearly does.
  2. Is fire protection in service for the new work? If the tenant layout requires sprinkler relocation or additional heads, ceiling grid and partitions cannot go in over an unapproved sprinkler design, because that work will be concealed.
  3. Is egress from any occupied portion of the building maintained during construction? Temporary corridors, exiting, and fire department access must remain usable.
  4. How will the partial work be inspected before concealment? Establish inspection points up front.

If those conditions can be met, a limited authorization for defined interior framing with written conditions is defensible. If not, deny the request in writing with the specific reason. Either way, the authorization must not permit work that would later be hidden without inspection, and it must not be described as approval of the deferred items.

3. Three weeks later the sprinkler shop drawings arrive showing an NFPA 13R design. What is the correct response, and why is it not simply a shop-drawing comment?

Read the worked answer

The submittal is being used to change the design basis, not to detail it. NFPA 13R is a residential sprinkler standard and is not an acceptable substitute for the NFPA 13 system shown on the approved construction documents for a mercantile occupancy. Deferred-submittal review cannot be used to approve a lower level of protection than the code and the approved documents require.

Response: reject the submittal in writing, stating that the system basis must match the approved design; require revised sealed drawings and hydraulic calculations from the fire protection designer of record, then re-review as a design change. Check whether any code trade-off was taken on the strength of the NFPA 13 system, such as an area or height increase or a reduced fire-resistance element, because those trade-offs do not survive if the system basis changes.

If 13R components have already been installed, consult the building official about a stop-work order limited to the sprinkler scope and require removal or redesign. Record the sequence in the file: the original approval, the submittal, the rejection, and the resubmittal. That record is what protects the department if the tenant later claims the delay was the department's fault.