Deccan Ceramics: Project-Specific Discount Rate, Customer Concentration and a Phase II Option

CMA Final Paper 20A · Put your knowledge to work in context.

All case studies

Deccan Ceramics: Project-Specific Discount Rate, Customer Concentration and a Phase II Option

Deccan Ceramics Ltd is appraising a greenfield vitrified-tile plant. The CFO's model shows an outlay of ₹258 crore at year 0 - including ₹18 crore for emission-control equipment required by a consent condition - and level free cash flow of ₹59.6 crore in each of years 1 to 8, with no terminal value. At the group WACC of 12% this gives an NPV of ₹38 crore, and the board paper recommends approval on that basis. The plant is to be funded with ₹160 crore of project debt at 9.8% and ₹80 crore of equity, and the CFO has used the group rate rather than a project rate. A listed tile manufacturer with an equity beta of 1.60 and debt/equity of 0.50 is the closest comparable. The risk-free rate is 7.0%, the market risk premium 6.0%, and the tax rate 25.17%. Forty-five per cent of output is committed to one distributor under a four-year agreement that expires before the plant's life ends. Management also holds land and a consent to add a Phase II line for ₹90 crore in year 3.

1. Derive the project-specific WACC and re-compute the NPV. What do you conclude about the board paper?

Read the worked answer

Unlever the comparable

βu = 1.60 / [1 + (1 − 0.2517) × 0.50] = 1.60 / 1.3742 = 1.164

Relever at the project's capital structure (D/E = 160/80 = 2.0)

βL = 1.164 × [1 + 0.7483 × 2.0] = 1.164 × 2.4966 = 2.907

Ke = 7.0 + 2.907 × 6.0 = 24.44% Kd (after tax) = 9.8 × 0.7483 = 7.33% WACC = (1/3 × 24.44) + (2/3 × 7.33) = 8.15 + 4.89 = 13.04%

NPV at 13.04%

Annuity factor, 8 years at 13.04% = (1 − 1.1304⁻⁸) / 0.1304 = 4.792

NPV = (59.6 × 4.792) − 258 = 285.6 − 258 = +₹27.6 crore

Conclusion on the board paper. The project still clears its cost of capital, but the margin is ₹27.6 crore, not ₹38 crore - a 10.4% NPV-to-outlay ratio, which is thin for a greenfield plant with a single-machine dependency and a concentrated customer. The board paper overstates the cushion by roughly ₹10 crore because it applies a group rate to a project whose leverage (67% debt) and business risk are both higher than the group's. Two further weaknesses in method: a single constant WACC assumes the 2:1 structure is maintained for eight years, which is untrue for amortising project debt (APV would be more defensible); and the ₹18 crore emission-control spend is non-discretionary, so it belongs in the base case and cannot be treated as an optional add-on.

2. Quantify the exposure to non-renewal of the distributor agreement after year 4, and state the break-even assumption for the project to remain value-neutral at the project WACC.

Read the worked answer

Scenario: distributor exits after year 4. Assume free cash flow falls by 40% in years 5 to 8 (45% of output, allowing for partial replacement through other channels).

Discount factors: annuity factor years 1–4 at 13.04% = 2.972; years 1–8 = 4.792; therefore the years 5–8 factor = 1.820.

PV of the fall = 0.40 × 59.6 × 1.820 = ₹43.4 crore NPV becomes 27.6 − 43.4 = −₹15.8 crore

So the entire equity cushion is wiped out by a single foreseeable event: the expiry of a four-year contract on an eight-year asset.

Break-even. The NPV is extinguished by a fall in annual free cash flow of 27.6 / 1.820 = ₹15.2 crore, i.e. 25.4% of ₹59.6 crore, if it occurs in years 5–8. Given that one distributor accounts for 45% of output, a 25% volume loss is well within the plausible range.

Interpretation. The distribution of outcomes is skewed: the base case is a modest positive NPV, while the downside case is negative on a probability that is not remote. For a project of this size, the decision should turn on whether the distributor agreement can be extended or the concentration diversified before financial close; if neither, the base case should carry the 40% haircut in years 5–8 and the project should not proceed on the CFO's numbers.

3. Evaluate the Phase II option and recommend the approval structure the board should adopt.

Read the worked answer

The option. The land and consent to build a ₹90 crore Phase II line in year 3 constitute a growth option: management can decide in year 3 with information the market does not have and with the Phase I plant already operating. Standard DCF ignores it because the ₹90 crore is not committed today. Under a real-options framing, Phase II adds value equal to its own NPV at the year-3 decision date multiplied by the probability that it will be exercised, discounted back at the project rate - and it is asymmetric, because a poor Phase I outcome simply means not exercising.

Why it supports staging rather than a yes/no. Key considerations:

  1. The Phase I NPV of ₹27.6 crore is too thin to absorb a ₹258 crore irreversible outlay with 45% customer concentration. An irreversible commitment should demand a larger cushion.
  2. The Phase II option has value only if it is genuinely exercisable - the consent must not lapse, and the land must remain unencumbered.
  3. Option value is destroyed by committing to both phases now.

Recommended approval structure

  • Approve Phase I with stage gates: distributor agreement extended or replaced so that no single customer exceeds 30% of output before commissioning; uptime and yield tests at month 6 of operation.
  • Record Phase II as a separate investment case to be brought back at the end of year 2 with actual yield, energy cost and price realisation data.
  • Re-run the appraisal at 13.04% (not 12%), with the emission-control spend in the base case, and post-audit the assumptions 12 months after commissioning against the original model.
  • Disclose the customer concentration and the option as principal risks in the board papers, since they, not the discount rate, drive the decision.