Completion Certificates and Periodic Inspection Reports

Two different documents

A completion/installation certificate is issued for new work (new installation, alteration, addition) and certifies that the work complies with the wiring rules. A periodic inspection report is issued for existing installations at intervals, recording condition and any departures/defects. A frequent trap is asking which certificate is correct for a given scenario - new circuit โ‡’ completion certificate; routine check of an old installation โ‡’ periodic inspection report.

What a valid certificate contains

Know the anatomy: details of the client and installation, a schedule of test results (continuity, insulation resistance, polarity, earth-fault loop impedance, RCD operation), a schedule of items inspected, declarations/signatures, and the extent and limitations of the work or inspection. The certificate is only valid for the work described - a completion certificate for a new socket does not certify the whole house.

Classification of findings

Periodic reports use codes for observations, typically ranging from 'requires immediate action / dangerous' down through 'potentially dangerous - urgent' to 'improvement recommended' and 'does not comply with current standard but not dangerous'. Candidates must map a described defect to the right severity. Missing main earthing, exposed live parts or a failed RCD are immediate-danger items; an older cable colour code or absent supplementary bonding is often 'improvement recommended'.

Traps

Signing a certificate without the test results; certifying work you did not supervise; confusing 'satisfactory' with 'no observations' (a report can be satisfactory with coded improvements); assuming a periodic report makes the installation 'new'. Certificates must be issued to the person ordering the work and retained per the rules.

Rule of thumb: if the question is about new work, think completion certificate + test schedule; if it is about condition over time, think periodic report + coded observations.