CHSE Odisha VOC-ITV Construction Painter & Decorator: Surface Preparation and Substrate Assessment

CHSE Odisha VOC-ITV Construction Painter & Decorator · Work through your exam, one topic at a time.

All guide sections

Surface Preparation and Substrate Assessment

Preparation decides whether a paint film survives. The exam tests whether you can judge a substrate - plaster, concrete, brick, timber, steel, galvanised sheet or an old painted surface - and prescribe the correct preparation and primer.

Assessment checks

  • Moisture: masonry should read below roughly 12–15% on a moisture meter, and timber lower still. Damp walls blister and peel.
  • Alkalinity: new lime-bearing plaster is alkaline; a pH test above about 9 means alkali-resisting primer is required, not direct emulsion.
  • Efflorescence: white salt bloom is brushed off dry and the source of damp traced; washing pushes salts back in.
  • Timber: resinous knots need shellac knotting, or resin bleeds through; nail heads are punched and primed.
  • Steel: rust is scraped or wire-brushed to bare metal and covered at once with a rust-inhibitive primer.
  • Old paint: chalking, flaking and gloss are deglossed and feathered; unstable coats are stripped.

Sequence

Clean → repair cracks and holes → sand → dust off → prime → fill → sand → undercoat.

Worked example

A 12 m² internal wall reads pH 10 and 16% moisture. Reasoning: both readings fail, so no coating will hold. Correct instruction: find and cure the damp, let the plaster dry to below 12%, then apply one coat of alkali-resisting primer before two coats of emulsion. Painting now would guarantee blistering within one monsoon.

Traps that cost marks

Priming over damp; sanding old lead paint dry; skipping knotting; filling over dust; using emulsion as a primer on bare plaster; ignoring a hollow, blown patch.