Crashing a 16-Day Polytechnic Block to 13 Days Under Liquidated Damages

JSSC JE · Put your knowledge to work in context.

All case studies

Crashing a 16-Day Polytechnic Block to 13 Days Under Liquidated Damages

An additional classroom block for a government polytechnic must be handed over in 13 working days to avoid a liquidated-damages clause of ₹10,000 per day. The approved network has five activities: A (site clearance, 3 days) precedes B (foundation, 5 days) and C (plinth beam and columns, 4 days); B and C both precede D (roof slab, 2 days); D precedes E (finishing, 6 days). The contractor's planning cell reports these crash options within the same sequence: A can be shortened by 1 day at ₹6,000 per day, B by 2 days at ₹4,000 per day, C by 1 day at ₹3,000 per day, D by 1 day at ₹5,000 per day, and E by 2 days at ₹8,000 per day. Normal completion is 16 days. The executive engineer must approve the least-cost crash plan that delivers the block in 13 days, and must also answer the contractor's alternative proposal to crash E by two days instead of touching the structural activities.

1. Identify the critical path, the project duration and the float available, and state how much time must be recovered.

Read the worked answer

Two paths exist:

  • Path 1: A–B–D–E = 3 + 5 + 2 + 6 = 16 days
  • Path 2: A–C–D–E = 3 + 4 + 2 + 6 = 15 days

Critical path is A–B–D–E at 16 days. A, B, D and E have zero total float; C has 16 − 15 = 1 day of float.

Time to recover = 16 − 13 = 3 days, to avoid 3 × ₹10,000 = ₹30,000 of liquidated damages.

The trap in this network. Crashing an activity shortens the project only while it lies on the critical path. Path 2 is only 1 day behind, so more than one day of crashing B alone buys nothing beyond the first day - the moment path 1 drops to 15, C becomes critical and further work on B is wasted money. Every crash decision must be re-checked against both paths, which is why a simple 'cheapest activity first' answer is wrong.

2. Work out the least-cost plan to reach 13 days and show its economics.

Read the worked answer

Cheapest combination. Let reductions be a, b, c, d, e. The constraints are:

  • Path 1: a + b + d + e ≥ 3
  • Path 2: a + c + d + e ≥ 2 with limits a ≤ 1, b ≤ 2, c ≤ 1, d ≤ 1, e ≤ 2.

A, D and E appear on both paths (shared); B helps only path 1, C only path 2. Cheapest solution: a = 1, b = 1, d = 1.

Cost = 6,000 + 4,000 + 5,000 = ₹15,000. Check: Path 1 = 2 + 4 + 1 + 6 = 13 ✓; Path 2 = 2 + 4 + 1 + 6 = 13 ✓ (C stays at 4).

Economics. LD avoided = 3 × ₹10,000 = ₹30,000, crash cost ₹15,000 → net benefit ₹15,000.

Alternative for comparison. Crash B by 2 (₹8,000) → path 1 = 14, path 2 = 15, but the project is now 15, so 2 days of B bought 1 day. Then C by 1 (₹3,000) → both 14; then D by 1 (₹5,000) → 13. Total ₹16,000 - feasible but ₹1,000 dearer. Recommend A + B + D at ₹15,000.

3. The contractor proposes crashing E by two days instead of touching structural activities. Evaluate the cost and the engineering judgement.

Read the worked answer

Arithmetic. Crash E by 2 days at ₹8,000 = ₹16,000. Path 1 = 16 − 2 = 14; path 2 = 15 − 2 = 13. The project becomes 14 days, not 13 - E is on both paths but path 1 still governs, so 2 days of crashing yields only 2 days of time.

Value: LD avoided 2 × ₹10,000 = ₹20,000 against ₹16,000 → net ₹4,000, compared with ₹15,000 net for the A + B + D plan. On money alone it loses.

Engineering judgement. E is 6 days of finishing compressed to 4, at the highest rate in the table. Finishing is labour-bound and moisture-bound: adding shifts to plaster, curing and painting is precisely where rework, shrinkage cracks and leakage complaints come from, and the ₹8,000/day rate understates that risk. E is worth using only when cheaper, shared activities are exhausted - its cost, ₹8,000, is still below the ₹10,000 LD rate, so it is not forbidden, just last in the queue.

Recommendation. Approve A + B + D for ₹15,000; hold E in reserve only if the structural activities turn out to be un-crashable on site.