Vidarbha Auto Components: Supplier A or Supplier B on total cost, not on price

Maharashtra HSC Logistics Supply Management (Vocational) · Put your knowledge to work in context.

All case studies

Vidarbha Auto Components: Supplier A or Supplier B on total cost, not on price

Vidarbha Auto Components, a Tier-2 supplier in Pune, buys 96,000 machined bushes a year over 300 working days for a customer line that stops when stock runs out. The part has no approved alternate. Purchasing has two quotes. Supplier A, Rajkot: ₹182 per piece ex-works, freight ₹18 per piece, 12-day lead time, 2.5% rejection at goods-in, 30-day credit, no minimum order. Supplier B, Nashik: ₹196 ex-works, freight ₹6 per piece, 5-day lead time, 0.6% rejection, 45-day credit, minimum 2,000 pieces per schedule. Every rejected piece costs ₹250 in sorting, rework and line disruption. The company's cost of capital is 12% a year. The plant head wants to stay with A because its unit price is ₹14 lower; the quality head wants B; the CFO wants a number, not an opinion. Both suppliers can handle the full annual volume, and B's rejection rate has held steady for eight quarters.

1. Build a total cost of ownership (TCO) comparison per piece for A and B, and state which supplier is cheaper on the numbers. Show every step.

Read the worked answer

Step 1 - Landed price. A: 182 + 18 = ₹200.00. B: 196 + 6 = ₹202.00.

Step 2 - Expected quality cost. Rejection % × ₹250. A: 0.025 × 250 = ₹6.25. B: 0.006 × 250 = ₹1.50.

Step 3 - Pipeline (in-transit) inventory. Daily demand = 96,000 ÷ 300 = 320 pieces. In-transit stock = 320 × lead time. A: 3,840 pieces × ₹200 = ₹7,68,000; at 12% = ₹92,160/year = ₹0.96 per piece. B: 1,600 pieces × ₹202 = ₹3,23,200; at 12% = ₹38,784/year = ₹0.40 per piece.

Step 4 - Credit benefit. B gives 15 extra days on annual spend of ₹202 × 96,000 = ₹1,93,92,000. Value = 1,93,92,000 × 0.12 × 15 ÷ 365 = ₹95,632 ≈ ₹1.00 per piece in B's favour.

TCO per piece

Element A B
Landed price 200.00 202.00
Quality 6.25 1.50
Pipeline carrying 0.96 0.40
Extra credit 0.00 (1.00)
TCO 207.21 202.90

Annual gap: (207.21 − 202.90) × 96,000 = ₹4,13,760 in favour of B. B's shorter lead time also reduces safety stock, which is not yet credited, so ₹4.13 lakh is a floor rather than a ceiling. Note the trap: A's ₹14 lower price is more than cancelled by ₹4.75 of quality cost, ₹10 of freight and ₹0.32 of extra pipeline stock.

2. Should the company single-source with B? Recommend a sourcing structure and the commercial terms it should put to A.

Read the worked answer

No. A 2.1% TCO advantage does not justify a single source for a no-alternate part feeding a line that stops. Single sourcing removes the benchmark that keeps B honest, and one fire, strike or tooling failure at Nashik idles the customer line.

Recommended structure: 70:30 split, B primary, A secondary, reviewed quarterly. Keep A alive on 30% so it stays approved and competitive, and tell A exactly why it lost the volume - this is the leverage that produces a real price.

What A must close: ₹4.31 per piece. Managable routes: ₹2 of freight (consolidate to full-truck loads), rejection from 2.5% to 0.6% (worth ₹4.75), or two days off lead time. Set the ask as '₹200 landed with ≤1% rejection and 9-day lead time', not a bare price cut.

B's terms to watch: MOQ 2,000 pieces = 6.25 days of demand, so schedule weekly, not monthly, or the credit advantage is eaten by extra stock. Verify B can hold 96,000 pieces and check its own sub-supplier and power backup. Build a written SLA with rejection above 0.6% debited at ₹250 per piece, and a 12-month price-hold clause.

B's 45-day credit is worth ₹1.00 per piece only if it is actually taken - confirm the payment run honours it rather than paying early.

3. Which three assumptions could reverse your answer, and what would you verify before signing?

Read the worked answer
  1. The ₹250 rejection cost. This is a goods-in estimate. If a rejected bush escapes to the customer line, the cost is a stoppage, not a sort, potentially ₹2,000+ per piece. At that level A's 2.5% is fatal and the case for B becomes overwhelming. Verify against the last 12 months of line-stop and debit-note data.

  2. Whether freight is paid on rejected pieces. If it is, add 18 × 2.5% = ₹0.45 to A. Also check whether rejected pieces are returned free or scrapped, and who pays return freight.

  3. Rate stability and capacity. Freight and steel prices move; a ₹6 per piece rise in B's freight more than wipes out the ₹4.13 lakh annual gain. Verify whether B's quote is firm for 12 months, whether B has spare capacity for 96,000 pieces, and whether A's ₹182 is ex-works only because it is quoting below cost to hold the part.

Also confirm the 12% cost of capital is the rate the CFO actually applies, and test sensitivity: at 18% capital cost, the pipeline and credit effects shift by roughly ₹0.48 per piece, which changes the size but not the direction of the decision.