PSEB SS Defence Studies study materials
PSEB SS Defence Studies study resources

Helicopter Sortie at a Cut-Off High-Altitude Post

PSEB SS Defence Studies · Put your knowledge to work in context.

All case studies

Helicopter Sortie at a Cut-Off High-Altitude Post

You command a forward post at 3,800 metres in a high-altitude sector with 42 personnel. A landslide has blocked the only road; the engineer estimate is nine days to reopen. You hold 18 days of kerosene, 11 days of dry rations and three days of fresh vegetables. At current consumption your generator fuel lasts 11 days. The weather forecast gives a single three-hour helicopter window tomorrow with a payload limit of 900 kg. Two soldiers show suspected frostbite and need evacuation. The district administration has asked you to deliver 200 kg of medical supplies to a village of 60 families cut off six kilometres away. The helicopter cannot simultaneously evacuate the casualties and carry a full supply load. Temperature is minus 14°C and falling, and the village has reported two cases of pneumonia.

1. How should the single helicopter sortie be tasked? State your decision and justify it by reference to at least two principles of military decision-making.

Read the worked answer

Decision: Use the sortie to evacuate the two frostbite casualties and carry a reduced emergency load of about 400–500 kg for the village, not the full 200 kg on top of the casualties. Reasoning: (1) Selection and maintenance of aim: the post exists to hold the border position; untreated frostbite can cause permanent loss of two trained soldiers, while the village pneumonia cases can be stabilised with a smaller cache of antibiotics and oral rehydration salts. (2) Economy of effort: a 900 kg payload cannot do everything; attempting both at full load risks overloading at high density altitude, where lift is reduced. (3) Humanity and civil-military legitimacy: a visible partial delivery, with a clear promise of a second sortie, preserves trust better than an unexplained refusal. Action: ask the district administration to cut its request to 120 kg of life-saving items, ask the helicopter crew to confirm payload at altitude, and record the decision in writing to higher headquarters.

2. What concrete measures will you take over the next nine days to sustain the post and manage the district administration's expectations?

Read the worked answer

Sustainment: Cut generator use to six hours per day for radio watch and medical heating only; this extends 11 days of fuel to about 16. Move rations to a heated store to prevent freezing and set a water-melting roster. Readiness: Set a 48-hour re-supply trigger and prepare a 200 kg man-pack cache for evacuation if the road slips again. Civil relations: Send a written situation report to the district magistrate with three facts - casualties evacuated, 120 kg delivered, next review in 48 hours. Offer the sarpanch a daily radio link and ask the village health worker to report pneumonia cases. Risk control: Do not promise a second helicopter until the weather window is confirmed. Decision rule: If fuel falls below seven days before the road opens, reduce patrols to one section and request an emergency airdrop.