M25 Column Batch with Hidden Mixing Water

SSC JE Civil · Put your knowledge to work in context.

All case studies

M25 Column Batch with Hidden Mixing Water

A site engineer at a residential project in Nagpur is casting M25 grade columns. The site mix board shows a nominal mix of 1:1.5:3 by volume and a water-cement ratio of 0.50. For one batch, the operator uses one 50 kg cement bag, 75 kg of sand, 150 kg of 20 mm coarse aggregate, and 25 litres of water. The sand has a moisture content of 4% and the coarse aggregate 1%. Cube samples taken at 7 days give an average compressive strength of 16 MPa. The contractor wants to continue casting because the 28-day result is expected to reach 25 MPa. The client's specification requires M25 concrete and permits no more than a 5% deviation from the specified batching water. You must decide whether to allow the next pour, order a retest, or reject the batch.

1. Calculate the actual water-cement ratio of the batch after accounting for aggregate moisture. Show each step.

Read the worked answer

Cement = 50 kg. Added water = 25 litres, so added water mass is about 25 kg.

Free moisture in sand = 4% of 75 kg = 3.0 kg. Free moisture in coarse aggregate = 1% of 150 kg = 1.5 kg.

Total effective water = 25 + 3.0 + 1.5 = 29.5 kg.

Actual w/c = 29.5 / 50 = 0.59.

Deviation from the specified 0.50 = (0.59 - 0.50) / 0.50 = 18%. This is well beyond the permitted 5% deviation. The batch is not being produced at the approved water-cement ratio even though the operator believes only 25 litres was added.

2. The 7-day cube average is 16 MPa. Using normal strength development, assess whether the batch can be accepted for the next pour.

Read the worked answer

For M25 concrete, 7-day strength is normally about 65-70% of 28-day strength, i.e. roughly 16.3-17.5 MPa. A value of 16 MPa is at or below the lower end of that range. More importantly, the actual w/c is 0.59 instead of 0.50, so the 28-day strength is likely to fall below 25 MPa unless the cement content or curing compensates.

A 7-day result alone should not be used to accept the batch, but it is enough to stop further pouring until the mix is corrected. The correct action is to suspend the next pour, keep the suspect concrete under observation, verify 28-day cube results, and if necessary order cores or other investigation. Continuing because the 28-day result is 'expected' to be 25 MPa is not a safe judgement.

3. State the immediate corrective actions before casting resumes.

Read the worked answer
  1. Stop batching by volume and move to weigh batching for cement, sand, aggregate and water.
  2. Measure free moisture in sand and aggregate at least once per shift, and subtract it from the added water. For this batch, added water should be reduced by about 4.5 kg to bring effective water back toward 25 kg for the same cement content.
  3. Check the actual cement content and batch yield; do not simply add extra cement without redesigning the mix.
  4. Prepare a trial mix at the corrected w/c, cast cubes, and obtain early and 28-day results before resuming structural pours.
  5. Record all corrections in the batch register and inform the client's engineer in writing.