Tamil Nadu HSE Second Year Basic Civil Engineering study materials
Tamil Nadu HSE Second Year Basic Civil Engineering study resources

Tamil Nadu HSE Second Year Basic Civil Engineering: Surveying and Levelling

Tamil Nadu HSE Second Year Basic Civil Engineering · Work through your exam, one topic at a time.

All guide sections

Surveying and Levelling

Surveying questions in this paper concentrate on converting compass bearings, computing reduced levels by the height-of-instrument method, and identifying the right instrument or correction for a described situation.

Chain survey and bearings

  • The base line is the longest line, measured most carefully; triangles should be well conditioned (angles between 30° and 120°). Offsets may be perpendicular or oblique.
  • Whole circle bearing (WCB) is measured clockwise from magnetic north, 0° to 360°. Reduced bearing (RB) is 0° to 90° with a quadrant letter.
  • Conversion: WCB 120° → RB = 180° − 120° = S 60° E. WCB 250° → RB = 250° − 180° = S 70° W. WCB 300° → RB = 360° − 300° = N 60° W.

Levelling

  • Principle: the line of collimation is horizontal, so HI = RL + back sight, and RL = HI − intermediate sight or fore sight.
  • Arithmetical check: ΣBS − ΣFS = last RL − first RL.
  • Curvature and refraction combined correction = 0.0673 d² (d in km); refraction alone is about one-seventh of curvature.

Worked example

BM RL = 100.000 m. BS 1.585 → HI = 101.585 m. IS 2.345 → RL = 101.585 − 2.345 = 99.240 m. FS 1.870 → RL = 101.585 − 1.870 = 99.715 m. Check: ΣBS − ΣFS = 1.585 − 1.870 = −0.285; last RL − first RL = 99.715 − 100.000 = −0.285. The booking is correct.

Marks-losing traps

  • Forgetting that a staff held inverted against a ceiling gives a negative reading.
  • Reporting a magnetic bearing as a true bearing without applying declination.
  • Mixing the rise-and-fall method with the HI method in one table, so the arithmetic check fails.