UPMSP Class 12 Business Studies study materials
UPMSP Class 12 Business Studies study resources

UPMSP Class 12 Business Studies: Controlling

UPMSP Class 12 Business Studies · Work through your exam, one topic at a time.

All guide sections

Controlling

Meaning and link with planning

Controlling is measuring actual performance against standards, finding deviations and correcting them. Planning is prescriptive and controlling is evaluative; planning looks ahead while controlling looks back and also forward, because corrective action shapes future performance. They are called the inseparable twins of management.

Features

Goal-oriented, pervasive, both backward- and forward-looking, continuous, dynamic and action-oriented.

The control process

Setting standards → measuring performance → comparing performance with standards → analysing deviations → taking corrective action. Two refinements sit inside comparison: critical point control (watch key result areas) and management by exception (act only on deviations beyond an acceptable range).

Worked example

Standard output is 1,000 units; actual output is 900 units. Deviation = −100 units, that is −10%. If the acceptable range is ±5%, corrective action is required: analyse causes such as machine breakdown or absenteeism, then act. Writing out the cause analysis before the remedy is what earns full marks.

Traps that cost marks

  • Claiming controlling ends the management cycle; it feeds back into planning.
  • Mixing management by exception (deviations beyond limits) with critical point control (key result areas).
  • Forgetting that minor deviations within range may be ignored.
  • Skipping the analysis step and jumping straight to punishment or correction.