WBBSE Madhyamik Vocational Construction study materials
WBBSE Madhyamik Vocational Construction study resources

WBBSE Madhyamik Vocational Construction: Setting Out and Measurement

WBBSE Madhyamik Vocational Construction · Work through your exam, one topic at a time.

All guide sections

Setting Out and Measurement

Domain 5 covers Setting Out and Measurement: transferring a drawing to the ground accurately and then recording site measurements correctly. Marks are lost for using the wrong reference line or the wrong unit.

Setting out a building

  • Fix two reference pegs for the front line and mark the centre line of the outer wall.
  • Use the 3-4-5 method to set a right angle: measure 3 m along one line, 4 m along the other, and adjust until the diagonal is exactly 5 m.
  • Set the remaining corners, then check both diagonals; they must be equal for a true rectangle.
  • Mark foundation trenches from the centre lines by adding half the wall thickness plus the offset for working space.
  • Use batter boards and string lines outside the excavation so the lines survive digging; transfer levels with a level or a hose pipe.

Measurement on site

  • Record in a field book: description, number, length, breadth and height, in metres to two decimals.
  • Units: linear m, area m², volume m³. Brickwork and concrete in m³, plaster and painting in m², steel in kg or quintal.
  • Measure brickwork between centre lines of walls and deduct openings above the specified size.

Worked example

A room is to be set out 6.00 m × 4.00 m. After fixing three corners with the 3-4-5 method, the diagonal is checked: √(6² + 4²) = √52 = 7.21 m. Reasoning: if the measured diagonal is 7.25 m, the corner is not 90°; shift the peg until both diagonals read 7.21 m within about 5 mm.

Traps

  • Measuring the trench from the outer face instead of the centre line.
  • Trusting one diagonal only.
  • Mixing millimetres and metres in the same measurement sheet.