Danger Tree Near a Power Line Under Wind Gusts

Master Craftsman Forestry · Put your knowledge to work in context.

All case studies

Danger Tree Near a Power Line Under Wind Gusts

A five-person manual felling crew is working a 12-hectare partial cut on a 25-degree slope. The stand contains dead and dying hemlock with root rot, and recent wind has left several lodged trees. A 12-metre right-of-way for a 25-kV power line runs along the lower boundary; one hemlock leaner is within 9 metres of the conductor. Forecast gusts are 45 km/h, and the crew leader has already seen debris fall from the canopy. The contractor’s production bonus rewards volume, and the client wants the unit finished before a rain event. A newly certified faller is assigned to the leaner because the senior faller is on another block. The faller says the tree “looks stable” and wants to fell it away from the line, but the escape route crosses a slash pile. No written danger-tree plan exists, and the utility has not been notified.

1. What is the immediate safety decision, and what authority and communication steps should follow?

Read the worked answer

The immediate decision is to stop work in the danger-tree zone and keep everyone out of the fall path and the power-line right-of-way. A 45 km/h gust, visible falling debris, a leaner within 9 metres of a 25-kV conductor, and an escape route blocked by slash are not conditions for a newly certified faller to improvise. The stop-work authority belongs to every worker, not only the supervisor; the crew leader should treat the tree as unsafe until a written plan and a qualified faller are in place.

The crew leader should notify the contractor and client that production is paused for safety, notify the utility of the leaner and the planned work, and establish an exclusion zone. If the line cannot be de-energized or protected, the utility or a qualified utility arborist should handle the tree. The newly certified faller should not be assigned the leaner merely because the senior faller is elsewhere. Record the stop-work, the reason, and the corrective action.

2. What alternative felling or removal methods would you consider, and what conditions must be met before any of them proceed?

Read the worked answer

The first alternative is to wait for lower wind and for the utility to de-energize or isolate the line. If that is not possible, use a mechanical feller buncher or an excavator with a grapple from outside the fall zone, or a winch-assisted directional fell with a qualified faller. The escape route must be cleared of slash and must lead away from the line and the lean. The tree should not be felled toward the conductor, and the crew should not stand on the downhill side where the butt may kick back.

Conditions before proceeding: a written danger-tree plan, a qualified faller or operator, a spotter, the utility’s approval and any required line protection, a clear exclusion zone, and a wind speed below the limit set by the employer’s safe-work procedure. If the lean, root rot, or lodged top makes the direction unpredictable, the tree should be pulled or machine-felled rather than manually felled. The production bonus is irrelevant to this decision; volume does not justify exposing a new faller to a line strike or a blocked escape route.

3. What professional and ethical issues does this situation raise, and how should they be documented?

Read the worked answer

The ethical issue is whether production pressure and client deadlines are being allowed to override a known serious hazard. Assigning a newly certified faller to a leaner near a power line without a plan, utility notification, or clear escape route is poor professional practice even if no incident occurs. The supervisor also has a duty to ensure the client understands why the unit may not finish before the rain event.

Documentation should include a stop-work notice, the hazard description, the weather conditions, the location relative to the conductor, the names of people informed, the utility notification, and the selected control method. A job hazard analysis or tailgate briefing should be completed when work resumes. If the contractor pressures the crew to proceed, the forester should escalate in writing and decline to certify the work as safe. The final record should separate the safety decision from production and show that the client was informed of the delay and the reason for it.