KS Public Adjuster: Property Loss Estimating and Claim Valuation

KS Public Adjuster · Work through your exam, one topic at a time.

All guide sections

Property Loss Estimating and Claim Valuation

This domain tests whether you can convert a scope of damage into a defensible number using line-item estimating conventions and correct valuation math.

Building the estimate

Estimates are built line by line: quantity × unit price, priced to the date of loss and the local pricing region. Each item belongs to a trade, and the total is assembled from the trades. Standard components include removal and disposal, labor minimum charges, material and labor, sales tax, permits, and equipment rental.

Concepts the exam presses

  • Replacement cost then depreciation. Compute replacement cost value (RCV) first, then subtract depreciation to reach actual cash value (ACV). On a replacement cost policy, the withheld depreciation is recoverable after repairs.
  • Overhead and profit. O&P is added where the scope requires a general contractor to coordinate multiple trades, commonly when three or more trades are involved. It is not automatic on every claim.
  • Matching. Where undamaged siding or roofing cannot reasonably be matched, the scope may need to extend to the matching area. Document the mismatch rather than asserting it.
  • Betterment and code upgrades. New-for-old advantages and ordinance-driven upgrades are handled through depreciation, ordinance or law coverage, and policy limits.
  • Salvage. Recoverable value reduces the loss.

Worked example

RCV of the repair is $24,000. Depreciation is $6,000 (25%). The policy has a $2,500 all-peril deductible and replacement cost coverage. The ACV payment is $24,000 − $6,000 − $2,500 = $15,500. When the insured completes the repair and documents the spend, the withheld $6,000 of recoverable depreciation is released, so the total paid approaches $21,500. The reasoning: the deductible is applied once, at the ACV stage, and depreciation is withheld rather than forfeited.

Traps that cost marks

  • Applying overhead and profit without evidence a general contractor is required.
  • Forgetting recoverable depreciation on an RCV policy.
  • Using today's pricing for an older loss date.
  • Double counting tear-out that is already embedded in a removal line.