Astana Expo Services LLP - Relevant Costing for a Fixed-Price Bid with a Penalty Risk

Kazakhstan CAP · Put your knowledge to work in context.

All case studies

Astana Expo Services LLP - Relevant Costing for a Fixed-Price Bid with a Penalty Risk

Astana Expo Services LLP is invited to bid for the logistics of a three-day international forum in September 2026. The client's ceiling is a fixed KZT 26,000,000, with a penalty of KZT 5,000,000 if the build is not completed 48 hours before opening; management assesses a 10% probability of late completion. The finance team prepared: direct materials KZT 16,000,000; specialist crew 400 hours at a recharge rate of KZT 15,000 per hour; variable event overhead KZT 1,200 per crew hour; apportioned head-office overhead KZT 2,500,000 (5% of revenue); design work already incurred and paid, KZT 2,000,000, with no alternative use; staging equipment purchased for KZT 8,000,000 with a committed resale value of KZT 5,000,000 immediately after the event, or identical equipment hired for KZT 3,400,000. The crew is 80% utilised; accepting the forum would require turning down another confirmed job that yields a contribution of KZT 3,500,000. Crew are paid KZT 9,000 per hour whether or not they work. The company's policy is to bid only where expected margin is at least 8% of the bid price.

1. Compute the minimum relevant cost of undertaking the forum, explaining the treatment of each cost item.

Read the worked answer

Relevant (incremental/opportunity) cost build-up

Item Amount (KZT) Reasoning
Direct materials 16,000,000 Incremental cash outflow
Crew labour 0 Paid KZT 9,000/hour regardless of activity; not incremental
Opportunity cost of crew 3,500,000 Taking the forum displaces a confirmed contribution of KZT 3,500,000; this is the true economic cost of the 400 hours
Variable event overhead 480,000 400 hours × KZT 1,200; varies with the job
Equipment 3,000,000 Lower of net purchase cost (8,000,000 − 5,000,000) and hire (3,400,000)
Design work 0 Sunk; paid and no alternative use
Apportioned head-office overhead 0 Not caused by the job; allocation only
Total relevant cost 22,980,000

Note the trap: the recharge rate of KZT 15,000 and the cash wage of KZT 9,000 are both irrelevant. Only the displaced contribution matters, and 3,500,000 is materially less than 400 × 15,000 = 6,000,000, so the bid is cheaper than the accounting schedule suggests.

Risk-adjusted cost = 22,980,000 + (10% × 5,000,000) = KZT 23,480,000.

Minimum price at the 8% policy margin = 23,480,000 ÷ 0.92 = KZT 25,521,739.

2. Should the company bid at the KZT 26,000,000 ceiling? Quantify the expected outcome and the probability of lateness at which the bid becomes marginal.

Read the worked answer

Expected value at the ceiling

  • Margin if on time: 26,000,000 − 22,980,000 = KZT 3,020,000
  • Outcome if late: 3,020,000 − 5,000,000 = KZT (1,980,000)
  • Expected margin: 0.9 × 3,020,000 + 0.1 × (1,980,000) = KZT 2,520,000, i.e. 9.7% of price

This clears the 8% policy threshold (minimum price KZT 25,521,739), so on expected value the bid is acceptable - but only by about KZT 480,000.

Break-even probability of lateness (p) (1 − p)(3,020,000) + p(−1,980,000) = 0 → 3,020,000 − 5,000,000p = 0 → p = 60.4%

The assessed 10% risk is far below break-even, so the decision is not finely balanced on risk alone. The real exposure is the downside: a single late completion converts a 11.6% margin into a KZT 1,980,000 loss, which is roughly two-thirds of the expected profit.

Recommendation. Bid at KZT 26,000,000 subject to negotiated protections: a cap on liquidated damages, penalty liability limited to delays caused by the company, milestone-based completion dates with client-caused relief, a binding resale contract for the equipment before purchase, and confirmation that the displaced job cannot be rescheduled into a different month.

3. What qualitative and contractual factors should the board weigh beyond the KZT 2,520,000 expected margin?

Read the worked answer

Strategic and relationship factors

  • The other confirmed job: declining it may damage a repeat client, and the KZT 3,500,000 contribution is certain whereas the forum's KZT 2,520,000 is expected value only.
  • Reference value of a flagship international forum versus reputational damage if the build is late in front of foreign delegations.

Operational and delivery risk

  • Crew are already 80% utilised; September is a peak period, so overtime, fatigue and quality risk are real, as is the risk of overrunning into the next engagement.
  • The 48-hour completion condition is tight for a three-day build; assess the critical path, supplier lead times and permit approvals.
  • Foreign participants bring visa, insurance, customs and data-handling obligations that can create cost not in the schedule.

Financial and cash-flow factors

  • KZT 8,000,000 cash outlay for equipment before recovery of KZT 5,000,000; the resale must be contractually committed, otherwise the relevant cost rises to KZT 3,400,000 (hire).
  • Payment terms: if the client pays after the event while materials and crew are paid before, working capital peaks.
  • Material price escalation clauses; a 10% rise in materials wipes out the expected margin.

Contract terms to negotiate

  • Cap on liquidated damages and exclusion of consequential loss; force majeure; extension of time for client or authority delays; variation pricing; and a clear acceptance protocol so that "completion" is objectively defined.