Charrette After the Contract

LEED Green Associate · Put your knowledge to work in context.

All case studies

Charrette After the Contract

A developer has committed to LEED Gold for a 12-story office tower. The general contractor was hired before schematic design finished, and the curtain-wall bid was awarded based on a baseline design. The energy model now shows heating dominates annual energy use, but the owner wants to spend the remaining sustainability budget on a rooftop PV array because renewables earn credits. The design team has one week to recommend a package before façade fabrication begins. The project is in a cold climate with a fossil-fuel boiler and a grid with moderate carbon intensity.

1. What integrative process step is missing, and what can still be done?

Read the worked answer

The missing step is early cross-disciplinary goal setting and systems analysis before major decisions were locked. The Integrative Process credit expects energy- and water-related analysis before schematic design, with the owner, architect, engineers, contractor, and key specialists in the same conversation.

What can still happen is a focused, decision-oriented workshop, not a generic charrette. Bring the façade fabricator, mechanical engineer, controls contractor, and owner together to test:

  • Envelope and glazing options against heating load, solar gain, daylighting, and cooling load.
  • Right-sizing the boiler and air-handling systems after load reduction.
  • No-cost and low-cost measures: setpoints, schedules, economizer, fan pressure reset, commissioning, and plug-load control.
  • Whether PV is being used to buy points or to reduce real carbon.

The team should document the analysis and the decisions, even if the formal Integrative Process credit is no longer fully achievable.

2. How should the team compare the PV array with an envelope upgrade?

Read the worked answer

Compare performance, not credit labels. The PV array produces electricity; in a heating-dominated building with a fossil boiler, it may offset little heating energy and therefore have a weaker carbon case than the owner assumes. An envelope upgrade can reduce heating demand, improve comfort, and possibly downsize mechanical equipment, but it can also reduce useful solar gain or increase cooling load depending on orientation and glazing properties.

The team should run model iterations and compare:

  • Annual EUI and peak demand.
  • Carbon emissions using the actual fuel mix.
  • Life-cycle cost and maintenance.
  • Credit impact across EA, EQ daylighting, and thermal comfort.
  • Schedule risk, since façade fabrication is imminent.

A smaller PV array plus a better envelope and commissioning package may outperform a large array on both carbon and cost. The recommendation should state the metric used, not just the point total.

3. How should the decision be documented for LEED and for the owner?

Read the worked answer

Document a traceable decision chain:

  • Owner Project Requirements and Basis of Design, updated to show the heating-dominated profile and the chosen performance targets.
  • Meeting minutes identifying participants, options modeled, and why options were rejected.
  • Energy model runs for baseline, envelope option, PV option, and combined package.
  • Cost and carbon comparison, including assumptions about fuel and grid.
  • A clear record of what was decided before façade fabrication and what remains open.

This supports the Integrative Process narrative and later Enhanced Commissioning. It also protects the owner if the predicted savings do not materialize, because the assumptions and tradeoffs are visible.