Sri Lanka Engineering Service Exam: General Engineering Knowledge and Engineering Practice: Contracts, Procurement and Compliance

Sri Lanka Engineering Service Exam · Work through your exam, one topic at a time.

All guide sections

General Engineering Knowledge and Engineering Practice: Contracts, Procurement and Compliance

General Engineering Knowledge and Engineering Practice tests the rules that decide whether a public works project is delivered lawfully: procurement procedure, contract administration, measurement and payment, quality assurance, occupational safety and environmental clearance.

Procurement and contract

  • Public procurement follows the national Procurement Guidelines; works above the prescribed threshold go to National Competitive or International Competitive Bidding.
  • Works bid documents commonly follow CIDA/ICTAD standard bidding documents, with FIDIC-type conditions on donor-funded contracts.
  • Bid security (commonly 1–2% of bid value) is released to unsuccessful bidders; performance security (commonly 10% of contract price) runs through construction.
  • Retention is typically 10% of each interim payment, capped at 5% of the contract sum.
  • Variations are valued at BOQ rates where the work is similar, otherwise at a new rate built up from labour, plant and material.

Environment and safety

  • The National Environmental Act requires an Initial Environmental Examination or EIA for prescribed projects, with approval from the Central Environmental Authority.
  • The Factories Ordinance and its regulations govern machinery guarding, scaffolding and safety officers.

Worked example

Contract sum Rs. 100 million, retention 10% capped at 5%. After a Rs. 30 million interim payment, retention held is Rs. 3 million; from the ninth payment onward it stops at Rs. 5 million. If the contractor abandons the works, the employer calls the performance security, while retention is applied to defects - it is not a penalty.

Traps

  • Treating bid security and performance security as the same instrument.
  • Granting extension of time for delay on a non-critical activity.
  • Certifying provisional-sum work as though it were a variation.
  • Confusing the defects liability period with the retention period.