Bid Margin Erosion on a Two-Level Roof

MN Roofing Contractor · Put your knowledge to work in context.

All case studies

Bid Margin Erosion on a Two-Level Roof

A roofer bids a 40-foot by 28-foot main gable at 6:12 and a 20-foot by 16-foot lower roof at 4:12. There are two valleys, eight penetrations, and two layers of tear-off. The estimator uses 18 squares, prices the job at $425 per square, and then adds 18% overhead and 12% profit to the selling price. Actual material cost is $3,200, labor is $2,800, and disposal is $600. The crew later discovers 15% waste from valleys and cuts. The homeowner wants a fixed price and a 10-year workmanship warranty. The roofer has one crew, three working days, and a $2,000 deposit. The roofer's target is a 12% net profit on sales, not on cost, and wants to know whether the bid is too low.

1. Calculate roof area in squares, including pitch, and compare with 18 squares.

Read the worked answer

Main footprint = 40 × 28 = 1,120 sq ft; 6:12 pitch multiplier = sqrt(1 + 0.5²) = 1.118; roof area = 1,252 sq ft. Lower footprint = 20 × 16 = 320 sq ft; 4:12 multiplier = sqrt(1 + 0.333²) = 1.054; roof area = 337 sq ft. Total = 1,589 sq ft = 15.89 squares. With 15% waste = 18.27 squares. The 18-square estimate is slightly low even before starter, ridge, and valleys; order at least 19 squares and verify actual field measurements. Two-layer tear-off is 31.8 squares of disposal, not 18.

2. Determine correct selling price for 12% profit on sales given costs, and explain markup vs margin.

Read the worked answer

Direct cost = $3,200 + $2,800 + $600 = $6,600. Overhead at 18% of direct cost = $1,188; total cost = $7,788. To earn 12% profit on sales, price = $7,788 / (1 - 0.12) = $8,850. The estimator's method, adding 18% then 12% to cost, gives $6,600 × 1.18 × 1.12 = $8,722.56. Profit is $934.56, or 10.7% of sales, not 12%. The difference is $127.44. Markup divides by cost; margin divides by price. For a target margin, always divide by (1 - margin).

3. Recommend how to handle waste and warranty risk.

Read the worked answer

Price 19 squares plus accessories, not 18. Carry a 15% waste factor for the valleys and cuts; add starter, ridge, drip edge, ice barrier, and boots. Use a fixed price with a written decking allowance (for example, first 10 sheets included, additional sheets at $95 each). Include a 10-year workmanship warranty only if the manufacturer's ventilation and installation requirements are met; state exclusions for deck movement and existing defects. Do not absorb the risk by cutting labor. A $2,000 deposit should be applied to materials, with progress payments after tear-off and dry-in.