MoP Practitioner: Portfolio Definition and Delivery Practices

MoP Practitioner · Work through your exam, one topic at a time.

All guide sections

Portfolio Definition and Delivery Practices

This domain tests the sequence and outputs of the five definition practices and the purpose of the seven delivery practices. Scenario questions typically describe a problem and ask which practice should address it.

The definition cycle

  1. Understand the strategic objectives, the BAU baseline, the current change landscape and the benefits being sought.
  2. Categorize initiatives so that like is compared with like, for example by strategic goal, business unit, risk or investment type.
  3. Prioritize using agreed criteria and scoring; distinguish must-do, should-do and could-do work.
  4. Balance the portfolio mix across strategic coverage, risk, resource, time horizon and change versus BAU.
  5. Plan the portfolio through portfolio, delivery, resource, financial and benefits plans.

The delivery practices

  • Management control: monitoring, gated reviews, assurance and corrective action.
  • Benefits management: benefits profiles, realization plans, owners and reviews.
  • Financial management: funding, budgeting, cost control and investment appraisal.
  • Portfolio risk management: aggregated risk, appetite and coordinated responses.
  • Stakeholder engagement: communication, involvement and expectation management.
  • Organizational governance: decision rights, escalation and alignment with corporate governance.
  • Resource management: demand versus capacity, scheduling and scarce skills.

Worked example

A bank must deliver a regulatory change and a revenue-generating app. Prioritization cannot rank the app above the mandatory regulatory work; the criteria must recognize compliance as a must-do. Balance then checks that the portfolio is not overloaded with high-risk change, and planning converts the decisions into a funded, resourced schedule.

Traps

  • Prioritizing before categorizing, producing meaningless comparisons.
  • Treating balance as a second round of prioritization.
  • Assuming benefits management ends at project closure.
  • Treating portfolio risk as simply the sum of project risks.
  • Defining the portfolio once and never refreshing it.