This domain tests whether findings are clear, supported, and actionable, and whether communication continues through management responses and verified remediation.

Core rules and concepts

  • An engagement report typically states objectives, scope, results, conclusion, and recommendations, with management responses.
  • A finding should link criteria, condition, cause, and effect. The effect states the risk or exposure, not merely that a policy was breached.
  • Recommendations should identify an action, an owner, and a target date. Avoid prescribing detailed operational design when management is responsible for the solution.
  • Communicate throughout the engagement, including an exit discussion, so factual errors are corrected before final issuance.
  • Follow-up verifies implementation, not just management's promise. Overdue high-risk actions are escalated to the board or audit committee.
  • Conclusions must stay within the engagement scope; do not imply an overall opinion when only one process was tested.

Worked example

A draft says "procurement controls are poor." It has no criterion or effect. A stronger finding states: policy requires three quotes above $50,000; eight of forty sampled purchase orders had one quote; the system does not block single-quote orders; this exposed about $1.2 million to noncompetitive pricing. The recommendation assigns the procurement director to configure a system block by a stated date, with follow-up evidence required.

Traps that cost marks

Issuing recommendations without owners or dates; reporting only at the end; accepting a response without testing implementation; and overstating conclusions beyond the scope tested.