The Extra Reports: Constructive Change or Unauthorized Work?

NCMA CPCM · Put your knowledge to work in context.

All case studies

The Extra Reports: Constructive Change or Unauthorized Work?

Alpha Solutions holds a $2.4 million firm-fixed-price contract for program management support. The performance work statement requires one monthly status report, not to exceed four pages. In month 3, the contracting officer's technical representative emails the project manager asking for a weekly dashboard plus ad hoc data calls, saying the additional reporting is 'needed for the good of the program.' Alpha performs 40 additional reports and data calls over five months, incurring $18,600 in labor. Alpha's project manager mentions the extra work in month 7 to the contracting officer, who says no additional funds are available and that the COTR had no authority to order the work. Alpha submits a request for equitable adjustment for $18,600. The COTR's email did not include a contract modification number, and the contract's changes clause states that only the contracting officer may direct changes in writing. Alpha did not submit a written notice when the COTR first asked for the extra reports.

1. Is Alpha entitled to an equitable adjustment? Analyze the changes clause, the COTR's authority, and the effect of Alpha's delay in notifying the CO.

Read the worked answer

Entitlement is not automatic, but Alpha has a credible constructive-change argument. The changes clause says only the CO may direct changes in writing. The COTR lacked actual authority to order extra reports or commit funds. However, a constructive change can arise when government personnel direct work outside the contract and the contractor reasonably believes the direction is authorized. The COTR's email was an official direction tied to the program, and Alpha performed 40 additional reports over five months.

Alpha's delay in notifying the CO cuts against it because the contract required written notice and the government lost the chance to stop the work early. The CO should separate two questions: Was the extra reporting outside the PWS? If it was within the PWS's broad reporting requirement, there is no change. If it was outside, Alpha may recover the reasonable cost of the extra work, but the CO may reduce recovery for costs that could have been avoided with timely notice. The CO should not deny solely because the COTR lacked authority.

2. What should the CO do now? Consider ratification, funding, and documentation.

Read the worked answer

The CO should investigate before paying or denying. First, compare the COTR's requests with the PWS to determine whether the weekly dashboard and data calls were already required. Second, obtain Alpha's records showing the 40 reports, labor hours, and $18,600 cost. Third, determine whether funds are available and whether ratification is in the government's interest.

If the work was outside scope and the government accepted the benefit, the CO may ratify the unauthorized commitment if within authority, or negotiate a settlement. The CO should issue a modification only after finding a proper basis, and should not simply tell Alpha that the COTR lacked authority and refuse to pay. The CO should also document the notice delay and any prejudice to the government. A unilateral denial without analysis invites a claim and may weaken the agency's position.

3. What should the COTR have done differently, and what control should the office adopt?

Read the worked answer

The COTR should have routed the request to the CO before asking for extra reports, and should have avoided language suggesting the work was required. The office should adopt a control requiring CO review of any request that changes reporting frequency, deliverables, or level of effort. The COTR should receive written training on authority limits.

The CO should also track unofficial directions and require contractors to notify the CO when they believe they are performing extra work. This control protects both sides: it lets the government stop unnecessary work early and gives the contractor a clear path to an equitable adjustment.