Mechanical Room Combustion Air and Gas Piping

NM Journeyman Plumber · Put your knowledge to work in context.

All case studies

Mechanical Room Combustion Air and Gas Piping

A mechanical room in a new dental office measures 10 ft by 12 ft with an 8-ft ceiling and is built with spray foam and weatherstripping, so it qualifies as tight construction. It contains a 120,000 Btu/h natural gas boiler and a 40,000 Btu/h natural gas water heater. The gas meter is 60 ft longest length from the room manifold at 7 in. w.c. and a 0.5-in. w.c. pressure drop. The contractor proposes a 1-in. Schedule 40 steel trunk and 1/2-in. branches to both appliances: 15 ft to the water heater and 20 ft to the boiler. The room has one 6-in. combustion air opening to the exterior and a louvered door to a conditioned hallway. The boiler has a 4-in. induced-draft vent that terminates 18 in. below an operable window. The building inspector has asked for combustion air and gas piping calculations before final inspection.

1. Evaluate the combustion air provision for the mechanical room. What corrections are needed?

Read the worked answer

The room volume is 10 x 12 x 8 = 960 cu ft. For tight construction using the indoor-air method, a common requirement is 50 cu ft of volume per 1,000 Btu/h of total input. The total input is 120,000 + 40,000 = 160,000 Btu/h, so the required volume is 160 x 50 = 8,000 cu ft. The room is far short of that, so it cannot rely on indoor air alone.\n\nOutdoor combustion air must be provided. With two permanent openings directly to outdoors, each opening is commonly sized at 1 sq in. of net free area per 4,000 Btu/h. That gives 160,000/4,000 = 40 sq in. net free area for each opening, one near the ceiling and one near the floor. A single 6-in. opening has only about 28.3 sq in. gross area, and louvers reduce that further, so it is not adequate. The louvered door to the conditioned hallway does not count as outdoor air unless the hallway itself has adequate volume and openings and the adopted code permits that arrangement. Provide two properly sized outdoor openings or an approved engineered combustion-air system.

2. Check the proposed gas piping sizes. Is the 1-in. trunk and are the 1/2-in. branches acceptable?

Read the worked answer

The total connected load is 120,000 + 40,000 = 160,000 Btu/h, or about 160 cu ft/hr for natural gas at roughly 1,000 Btu per cu ft. Using the longest-length method, the trunk must be sized for 160 cu ft/hr at 60 ft with the available pressure drop and gas specific gravity. A 1-in. Schedule 40 steel trunk at 60 ft and 0.5 in. w.c. drop is roughly in the 190 to 200 cu ft/hr range, so it is likely adequate for the connected load, but it should be checked against the exact adopted table and include fittings and future load.\n\nThe 1/2-in. branch to the water heater carries 40 cu ft/hr at 15 ft and is likely acceptable. The 1/2-in. branch to the boiler carries 120 cu ft/hr at 20 ft and is too small; a 1/2-in. line at that length is typically only around 90 to 100 cu ft/hr. The boiler branch should be increased to 3/4 in. and the calculation shown on the permit drawing. Do not rely on rule-of-thumb sizing; use the code table for the actual gas, pressure drop, and longest length.

3. What is wrong with the boiler vent termination, and what should be checked before final approval?

Read the worked answer

An induced-draft vent terminating 18 in. below an operable window is too close. Typical clearance requirements for a mechanical-draft appliance vent are at least 4 ft below, 4 ft horizontally from, or 1 ft above an operable window, door, or gravity air inlet. The vent must be relocated to meet the manufacturer's listing and the adopted code clearance.\n\nBefore final approval, verify the vent termination height above the roof, clearance to doors, windows, air intakes, gas meters, and regulators, and the approved vent material and slope. Confirm that the combustion air openings are permanent, properly sized in net free area, and protected with corrosion-resistant screens or louvers. Also verify the gas piping calculation, appliance connectors, sediment traps, shutoff valves, and the required final inspections. The mechanical room must not be closed up until the combustion air and vent corrections are inspected.