Datums and projections

Ohio horizontal control uses NAD83, current realization, and vertical control uses NAVD88. The Ohio State Plane Coordinate System has North and South zones and uses a Lambert conformal conic projection; Ohio law recognizes state-plane coordinates for describing locations when properly computed. GNSS-derived ellipsoid heights must be converted with a geoid model, such as GEOID18, to NAVD88 orthometric heights.

Scale factors and accuracy

State-plane grid distances differ from ground distances. The combined factor is the projection scale factor times the elevation factor; grid distance equals ground distance times the combined factor. Control surveys need redundant observations, adjusted networks, and documented accuracy at a stated confidence level. Ties to NGS CORS or published passive control should state epoch and datum.

Worked example

A ground distance is 1,000.000 ft. Projection scale factor = 0.99994; elevation factor = 0.99996. Combined factor = 0.99994 × 0.99996 ≈ 0.99990. Grid distance = 1,000.000 × 0.99990 = 999.900 ft. A crew that records 1,000.000 ft as the state-plane distance creates a 0.100-ft error before any other uncertainty.

Traps

Using ground distances directly in state plane; omitting the elevation factor; mixing NAD27 and NAD83; treating ellipsoid height as orthometric; and failing to check the geoid model or epoch. Exam questions often test the direction of the correction and the difference between scale and combined factors.