Drain Encroachment, Court Deadline and Resettlement

OPSC OCS · Put your knowledge to work in context.

All case studies

Drain Encroachment, Court Deadline and Resettlement

You are the Municipal Commissioner of a city with 1.2 million people. A High Court order requires removal of 1,200 structures encroaching on a natural drainage channel before the monsoon, 60 days away. The channel has narrowed from 30 metres to 7 metres; last year, 9,000 households were flooded. The settlements house 4,000 households, mostly daily-wage workers, and 600 shops. The only vacant resettlement site is 9 km away; it has water but no school, health centre or bus service. Affected families reject it. Local councillors demand a delay; environmental groups demand immediate demolition; a TV channel broadcasts an old video of a child drowning in the locality. Your engineering team says partial dredging can cut flood risk by about 35% but cannot eliminate it. The court has asked for a compliance report in 15 days.

1. What sequence of action will you propose in the 15-day compliance report?

Read the worked answer

Reasoning: The court deadline and the monsoon risk are real, but mass demolition without resettlement would create homelessness and likely be stayed or reversed. Partial dredging helps but leaves most risk. The report must show good-faith compliance, not just intention.

Sequence: First, begin immediate no-regret works: desilt and clear the worst blockages, repair culverts, remove recent unauthorised structures that are vacant or easily removable, and map the flood path. Second, classify all 1,200 structures by risk, age, vulnerability and availability of alternative shelter; publish the criteria. Third, phase removal: highest-risk dwellings closest to the narrowed channel first, with temporary rental assistance and transport; shops get a livelihood transition plan. Fourth, upgrade the resettlement site before moving families: school access, health camp, bus service and water. Fifth, report to the court with a realistic timeline, the 35% risk reduction from dredging, and the need for continued work. The aim is to comply progressively while avoiding a humanitarian crisis.

2. How will you negotiate with affected families and local councillors?

Read the worked answer

Reasoning: Affected families are not opposing flood protection; they are opposing displacement into a site that lacks basic services. Councillors reflect that anxiety and also face electoral pressure. Negotiation must offer credible alternatives and transparent eligibility.

Families: Hold ward-level meetings with maps, criteria and entitlement lists. Offer a choice between temporary rental support and the resettlement site, with a written timeline for school, health and transport. Prioritise the most vulnerable for immediate shifting. Set up a grievance desk with a fixed response time. Do not promise permanent housing that is not funded.

Councillors: Ask them to help identify genuine hardship cases and to communicate the flood risk. Separate legitimate demands for better resettlement from blanket delay. If they obstruct, continue dialogue but document the court order and the engineering evidence. The public message should be that the city is removing the highest danger first and will not leave families without a plan.

3. How will you communicate with the media and the court?

Read the worked answer

Reasoning: An old video of a drowning can inflame public emotion, while silence can be read as concealment. The court will assess whether the administration is acting in good faith and with due process.

Media: Acknowledge the flood risk and the tragedy behind the video without sensationalising it. Publish the phased plan, eligibility criteria, resettlement entitlements and helpline. Give weekly progress updates: structures removed, dredging completed, families shifted, services provided. Avoid blaming the affected families.

Court: File a factual compliance report with photographs? No external exhibits are needed here; describe the works and timelines in the report. State what has been done in 15 days, what will be done before monsoon, and what constraints remain. Ask for a realistic schedule if full removal is impossible. The report should show that life safety, due process and resettlement are being addressed together.