Decontamination Bypass at a Sewage-Contaminated School

OSHA 15-Hr Disaster Site Worker · Put your knowledge to work in context.

All case studies

Decontamination Bypass at a Sewage-Contaminated School

A school flooded by a sewage-contaminated river is being remediated. The site has a hot zone on the first floor with standing water and mold, a warm zone with one decon line, and a cold zone with a break trailer. Forty workers are on a 10-hour shift. A laborer exits the hot zone through a side door, carrying a contaminated pry bar and wearing a Tyvek suit, and walks across the cold zone to the break trailer to refill his water bottle. Another worker removes his respirator inside the warm zone before doffing his coverall, then eats a sandwich without washing his hands. The decon line has one rinse tub, no soap, and no collection container for disposable suits; runoff flows toward a storm drain. A supervisor says the schedule is behind and asks whether these are minor issues.

1. Identify the decontamination and site control breaches and explain why each matters.

Read the worked answer

These are not minor issues. The laborer bypassed the decon line through a side door, carrying a contaminated pry bar into the cold zone; that spreads sewage and mold into clean areas and the break trailer. Wearing a Tyvek suit in the break trailer transfers contamination to door handles, tables, and water bottles. Removing the respirator in the warm zone before doffing the coverall is backwards: the respirator should stay on until the worker has left the contaminated area, because contaminants can be on the suit and hands. Eating without washing hands after doffing is an ingestion exposure. The decon line itself is inadequate: one rinse tub, no soap, no runoff collection, and discharge toward a storm drain violates containment. Under OSHA 1910.120, decontamination must prevent cross-contamination and protect the environment. These breaches can cause chemical and biological exposure to the worker, other workers, and the community.

2. Describe the correct decontamination sequence for the worker and for the pry bar.

Read the worked answer

For the pry bar: keep it in the hot zone until gross decontamination; wash it with detergent and water, rinse, dry, and bag or tag it as decontaminated before moving it to the clean side. For the worker: do gross decontamination at the hot and warm boundary by hosing off boots and suit; wash outer gloves; remove outer gloves; wash the suit; remove the suit by rolling it inside out; remove boot covers or wash boots; then leave the warm zone. Remove the respirator only after leaving the contaminated area, then wash hands and face and shower. Dispose of suits in a labeled container. The decon line should have a dirty-to-clean flow, soap and water, rinse water, and containment for runoff. A buddy should supervise the sequence. Any worker who bypasses decontamination should be stopped and the path cleaned.

3. What changes would you make to the site layout and supervision?

Read the worked answer

Redesign the site with one controlled access and egress point, a decon line with clear dirty and clean sides, soap, rinse, and a collection container. Keep the break area outside the cold-zone boundary until workers have showered or changed, and separate clean and contaminated tools. Post an attendant at the decon line with authority to stop workers. Train all 40 workers on the sequence and on the reason: sewage and mold are brought out on suits and tools. Provide water and shade near the break trailer so workers do not improvise. Schedule decontamination time into the 10-hour shift instead of treating it as optional. Fix the runoff by blocking the storm drain, diking, and pumping to a container. The supervisor should stop work until these controls are in place; schedule pressure is not a justification for spreading contamination.