DORA Lead Manager: Review and continual improvement

DORA Lead Manager · Work through your exam, one topic at a time.

All guide sections

Review and continual improvement

This domain tests how DORA obligations are monitored, reviewed and improved over time, including how evidence from incidents, testing and third-party monitoring feeds back into the framework.

Core rules and concepts

  • The ICT risk management framework is reviewed at least annually and after significant events or material changes. Reviews must be documented and approved by the management body.
  • Post-incident reviews and lessons learned should change controls, business continuity plans, monitoring thresholds and training, not just produce a report.
  • Testing results, including TLPT findings, must be remediated and tracked to closure. Repeated findings indicate a weak improvement loop.
  • Third-party monitoring continues through the contract lifecycle: service levels, audit reports, subcontracting changes, exit readiness and concentration risk.
  • Use metrics and key risk indicators, internal audit and management reporting to evidence continual improvement. Supervisory feedback should be incorporated into the roadmap.

Worked example

After a major incident, an insurer completes the final report but also updates its backup configuration, adds a provider escalation contact and changes its incident classification threshold. The reasoning: DORA's review cycle is not a documentation exercise. The incident revealed a control weakness, and the improvement must be evidenced through changed procedures, owners and follow-up testing.

Traps that cost marks

  • Treating the annual review as a tick-box policy refresh with no management-body approval.
  • Closing audit or testing findings without root-cause remediation and verification.
  • Ignoring third-party changes such as new subcontractors or data locations.
  • Failing to connect lessons learned to training, risk tolerance and future test scope.