Security Operations Management System (SOMS)

What this domain tests

Domain 2 covers the management system itself: the clause architecture, what must be documented, and how conformity is demonstrated through internal audit, management review and certification.

Skeleton of the standard

  • Clause 4 Context - internal and external issues, interested parties, scope of the SOMS.
  • Clause 5 Leadership - top-management commitment, policy, roles and authorities.
  • Clause 6 Planning - risks and opportunities, security and human rights risk assessment, legal and other requirements, objectives.
  • Clause 7 Support - resources, competence, awareness, communication, documented information.
  • Clause 8 Operation - operational planning and control, incident management, use of force, detention and handover of persons, supply-chain due diligence.
  • Clause 9 Performance evaluation - monitoring and measurement, internal audit, management review.
  • Clause 10 Improvement - nonconformity, corrective action, continual improvement.

Rules worth memorising

  • The policy must suit the organization's purpose, commit to human rights, the rule of law and continual improvement, be documented, communicated, and available to interested parties.
  • Objectives must be measurable, monitored and traceable to the risk assessments.
  • Documented information must be controlled: available where needed, protected, version-managed.
  • The audit programme is planned by risk and covers SOMS processes, not only guarding sites; management review uses audit results, incidents, grievances and performance data as inputs.

Worked example

A 60-guard firm fails its Stage 1 audit. Findings: the policy is signed by the operations manager rather than top management; objectives read "improve quality"; internal audit covered only guarding sites; management review minutes list no inputs. The fixes follow directly - policy approved at top level, objectives made measurable and time-bound, audit programme extended to support and planning processes, review agenda built from the standard's stated inputs. Reason: the auditor tests whether the system functions as a system, not whether individual guards perform well.

Traps that cost marks

  • A good policy that top management never approved or communicated.
  • Objectives with no baseline, target or measurement method.
  • Management review run as a site meeting instead of a strategic review with defined inputs.
  • Forgetting certification is a three-year cycle with surveillance audits.