Energy Performance in a Chiller Procurement Decision

PECB ISO 50001 Foundation · Put your knowledge to work in context.

All case studies

Energy Performance in a Chiller Procurement Decision

A brewery is replacing a 20-year-old ammonia chiller. The capital budget is €450,000, and the tender is at design stage. Option A is a like-for-like 1.2 MW chiller costing €380,000, with expected electricity use of 1.05 GWh per year. Option B is a 1.1 MW high-efficiency chiller with heat recovery costing €520,000, expected to use 0.86 GWh per year and to recover 0.4 GWh of heat that would otherwise be supplied by gas. Electricity costs €0.14/kWh and gas €0.05/kWh; both options have similar maintenance costs. The procurement policy requires selection of the lowest compliant capital bid. The project engineer says ISO 50001 only requires metering after installation and that energy performance is an operational issue. The sustainability manager wants energy performance included in the design and procurement decision. The company applies a four-year simple payback hurdle for energy projects.

1. How should ISO 50001 principles affect the design and procurement decision?

Read the worked answer

Energy performance should be considered at the design stage and in procurement, not after installation. The organization should include energy performance criteria in the specification and evaluate bids on life-cycle cost, not only capital cost. The choice between the two chillers should use expected annual energy, the value of recovered heat, maintenance and reliability, and any operational constraints. A simple comparison shows Option B saves about 0.19 GWh of electricity (€26,600/year) and displaces 0.4 GWh of gas (€20,000/year), giving roughly €46,600/year savings for about €140,000 extra capital-a simple payback of about three years, within the four-year hurdle. That justifies a life-cycle evaluation. The procurement policy should allow the higher-capital, lower-life-cycle-cost bid to win if it is compliant. The decision, criteria and assumptions should be documented.

2. What energy performance requirements should be written into the tender?

Read the worked answer

The tender should specify minimum efficiency at design conditions, expected annual energy consumption and the methodology for calculating it, part-load performance, heat-recovery output and temperature, refrigerant and safety requirements, controls and metering, commissioning and performance testing, and warranty. It should require the bidder to provide calculated annual energy use and the assumptions, so bids can be compared on a consistent basis. It should require measurement provisions-meters on the chiller and recovered-heat circuit-so savings can be verified. It should also state how performance shortfalls will be handled, such as performance testing and retention. These requirements turn energy performance into a contractual matter rather than an operational hope. The evaluation grid should weight life-cycle cost and verifiable performance alongside price and technical compliance.

3. How should the brewery verify the savings after installation?

Read the worked answer

Establish a baseline before replacement using existing meter data and operating records, adjusted for production and weather as appropriate. Define the measurement boundary: chiller electricity, recovered heat, and the gas that is displaced. Install meters or use existing ones to measure the new chiller's electricity and heat output. Compare post-installation performance with the baseline over a representative period, normalizing for production volume and ambient conditions. Use a simple measurement and verification approach proportionate to the project; a full regression may not be needed, but the assumptions should be documented. Check that heat recovery is actually used and not bypassed. Report the result against the business case and feed it into management review. If savings fall short, investigate whether the cause is design, commissioning, operation or the original estimate.