Management tests how IT work is planned, delivered, operated, controlled, and governed. It overlaps with project management, service management, risk, security governance, audit, and legal compliance.

Core rules and concepts

  • Project constraints: scope, time, cost, and quality; a change to one affects the others.
  • Planning tools: a WBS breaks deliverables into work packages; a Gantt chart shows schedule; PERT/CPM shows dependencies. The critical path is the longest path and has zero float.
  • Earned value: CV = EV − AC; SV = EV − PV; CPI = EV/AC; SPI = EV/PV. Negative CV or SV and ratios below 1 are unfavorable.
  • Service management: an incident restores service; a problem finds the root cause. Change management approves and schedules changes; an SLA defines service targets.
  • Risk response: avoid, transfer, mitigate, accept; then monitor. Transfer, such as insurance, does not eliminate the risk.
  • Continuity: RTO is the target recovery time; RPO is the tolerable data loss.
  • Governance and control: least privilege, segregation of duties, audit trails, and an ISMS based on ISO/IEC 27001.
  • Legal: software licenses, copyright, personal-data protection, and computer-crime law.

Worked example

A project reports PV = 100, EV = 90, AC = 110. CV = 90 − 110 = −20, so it is over budget. SV = 90 − 100 = −10, so it is behind schedule. CPI = 90/110 ≈ 0.82; SPI = 90/100 = 0.90. Both below 1 confirm the unfavorable position. The figures must be in the same currency unit; do not compare percentages across projects without checking the baseline.

Traps that cost marks

  • Confusing incident with problem.
  • Calling the critical path the shortest path.
  • Reversing RTO and RPO.
  • Treating risk transfer as risk elimination.
  • Confusing mitigation (reduce probability or impact) with avoidance (remove the threat).
  • Ignoring segregation of duties in internal-control questions.