The three surfaces

Geodetic work rests on distinguishing the topographic surface, the geoid (an equipotential surface approximating mean sea level, continued under the continents) and the reference ellipsoid. Ellipsoidal height h relates to orthometric height H through h = H + N, where N is the geoid undulation. Candidates must know the datums used in the Philippines: PRS92 uses the Clarke 1866 ellipsoid but is a geocentric, ITRF-aligned datum; Luzon 1911 used the same ellipsoid in a non-geocentric, locally fitting orientation; WGS84 uses GRS80. Datum transformation uses a 7-parameter Helmert (three translations, three rotations, scale) or the Molodensky formulas.

Coordinates, projections and scale

Geodetic latitude, longitude and height convert to ECEF X, Y, Z and back. For plane coordinates the Philippines uses UTM (Transverse Mercator, k0 = 0.9996, false easting 500 000 m), with Zone 50 (central meridian 117 deg E) and Zone 51 (123 deg E). Grid distance relates to ground distance through the combined factor: CF = scale factor x elevation factor, the elevation factor being approximately R/(R + H). Grid azimuth = geodetic azimuth minus the convergence.

Traps

Reversing the sign of N, omitting the elevation factor, confusing geodetic with geocentric latitude, and forgetting that spherical excess e = Area/R squared, in radians, is needed for large geodetic triangles.

Worked example. A line has grid length 1 000.000 m at 200 m elevation with scale factor 0.999 65 and R = 6 371 000 m. Elevation factor = 6 371 000 / 6 371 200 = 0.999 968 6. CF = 0.999 618 6. Ground distance = 1 000.000 / 0.999 618 6 = 1 000.382 m.