Jamuna Foods Ltd is evaluating a 5-year expansion requiring an initial outlay of Tk 60,000,000. Forecast annual operating cash flows are Tk 18,000,000. The company's weighted average cost of capital is 12%, but the project is in a new region and the finance team believes a risk premium of 3% is warranted. The company can borrow Tk 40,000,000 at 10% (interest deductible at 27.5%) and fund the rest from retained earnings. The board's stated policy is a 4-year payback. A director argues: 'The NPV is positive at 12%, so we should go; the risk premium is just conservatism.'

1. Evaluate the project using NPV at both discount rates and the payback rule. What is the correct decision and why?

Read the worked answer

Annuity factor, 5 years: at 12% = 3.6048; at 15% = 3.3522.

NPV at 12%: 18,000,000 × 3.6048 = 64,886,400 − 60,000,000 = +Tk 4,886,400.

NPV at 15%: 18,000,000 × 3.3522 = 60,339,600 − 60,000,000 = +Tk 339,600.

Payback: 60,000,000 / 18,000,000 = 3.33 years - within the 4-year policy.

Decision analysis. The project clears both hurdles, but the margin at the risk-adjusted rate is only Tk 339,600 - about 0.6% of the outlay. That is inside any reasonable forecast error. A 5% shortfall in annual cash flow (18,000,000 → 17,100,000) at 15% gives 17,100,000 × 3.3522 = 57,322,620, i.e. NPV −Tk 2,677,380. The project fails on a modest adverse variance.

On the director's argument: the risk premium is not 'conservatism' - it is the price of uncertainty in an unfamiliar region. Using the company WACC for a project of different risk is a classic error: the WACC reflects the average risk of existing operations. The correct discount rate is the one that reflects this project's risk.

Correct decision: do not proceed on the current case. The NPV at the risk-adjusted rate is too thin to be robust. Either renegotiate the outlay, secure a higher or contracted cash flow, or phase the investment to limit exposure. The payback rule passing is not decisive - payback ignores cash flows after the cutoff and the time value of money.

2. The finance team proposes using the 10% borrowing rate as the discount rate 'because that is what the project actually costs to finance'. Critically assess this.

Read the worked answer

This is the financing-mix fallacy. The discount rate in an NPV calculation should reflect the opportunity cost of capital for the project's risk, not the cost of the specific funds raised. Three reasons:

  1. It ignores the equity component. Tk 20,000,000 is funded from retained earnings, which carry an equity cost. Discounting only at the debt rate implies equity is free - it is not; shareholders forgo returns elsewhere.
  2. It ignores the tax shield correctly applied. The after-tax cost of debt is 10% × (1 − 0.275) = 7.25%, not 10%. Using the pre-tax rate overstates the cost of debt and understates the true WACC simultaneously - the errors do not cancel.
  3. It confuses source with use. How a project is financed affects the financing decision, not the investment decision. Mixing them lets a cheap loan make a bad project look good.

What the team should do: compute a project-specific WACC or, better, an asset-beta-based rate reflecting the new region's risk. If the debt is project-specific, the tax shield can be valued separately (APV approach), but the operating cash flows should still be discounted at an unlevered rate appropriate to the asset's risk.

Judgement tested: the candidate must recognise that 'this is the rate we actually pay' is not a valid basis for project appraisal, and must be able to articulate why the WACC, not the debt rate, is the starting point - and that the WACC itself must be risk-adjusted for a project outside the company's normal operations.